Search

Insertion of comments in P6

Forum Topic

Hi All, Could you throw some light on whether I can insert comments in any cells in P6 like we do in Excel? Thanks in advance for your replies.

Apr 6, 2011

activity duration

Forum Topic

What is the maximum accepted time duration for the activity, some ppl say 2 weeks some say 20 days and is there is any cod determine this period.   Thank you

Apr 7, 2011

critical path and loop

Forum Topic

Hi, I'm beginner in primavera; I just want to know how can I discover if there is any loop on the Critical path   Thank you

Apr 7, 2011

Synchro Issue

Forum Topic

Dear All,Good Day,I have encounter problem in importing IFC file to synchro stating (Error: cannot add 3D Entities to the Synchro project.)Please tell me how to solve or what is the cause of this error.Hoping for your help regarding this matter.Thank...

Apr 7, 2011

Totals in Original Duration Column giving wrong figure

Forum Topic

Myself and a colleague are using PM6 and have access to exactly the same programme schedule. However, on his system, the WBS totals for Original Duration are much higher than on my system. The activities within each WBS section show the correct durat...

Apr 7, 2011

How to stop automatic roll up of Activities

Forum Topic

Hi there, Does anyone know how to stop P5 from automatically rolling up my whole programme when I change the colour of a bar in the bars options?  Every time I expand the programme to show what I want and then alter something in the bars options and ...

Apr 7, 2011

NEC CONTRACTS CALLING ALL PLANNERS

Forum Topic

I would appreciate it if all planners Could share their experience in applying NEC contracts in dispute. MEPBuilding sevicesRail

Apr 7, 2011

Primavera Risk Analysis versus RiskyProject

Forum Topic

Hello there does anyone know anything about RiskyProject? We currently use Primavera Risk Anaylsis version 8.7 but since the upgrade the Capex Module cannot be used. Does RiskyProject have a Capex Module?

Apr 8, 2011

SDK

Forum Topic

Hello everybody,   Probably a this has been addressed in other threads too but I am a newbie & would really appreciate a detailed answer if possible.   How do u import a WBS from Excel to P6 ?   I know of the excel file ''PATTLNK_..........xls' Tried...

Apr 8, 2011

planned & actual S-curve VS EV

Forum Topic

Kindly advice if the client have the right to request from the contractor to show his resources in the submitted schedule , in case if he hasn't the right how the client or the consultant can evaluate the actual s curve and the EV. Thank you

Apr 9, 2011

contractors tricks in baseline schedule

Forum Topic

Hi experts, kindly i need to know the tricks which the contractors try to put in the baseline schedule and how i can catch it as a client. i appriciat everybody help on that. Thank you

Apr 9, 2011

Auto Organizer in P6

Forum Topic

Dear All, I want to stop the auto organization of Activities in P 6.0. The Fill option works only top to Down and not like P3 ( thats Ridiculous). Please help me in solving the problem. 

Apr 9, 2011

Changing sequence of work in updated programme

Forum Topic

Dear Planners,     while I am updating my programme of work I faced out of sequence activity, my question is that is it possible to change the relation ship of this activity because after scheduling the early finish of this activity is still be drive...

Apr 9, 2011

As Built Schedule Preparation

Forum Topic

Hello, In major construction Projects, after the initial base line is approved, extension of time is being  accorded many times according to delay events  and revised schedule continues to be submitted and approved. Some activities in the initial bas...

Apr 9, 2011

Desktop server

Forum Topic

Dear Experts please advice me on this query.. We are presently using the desktop server in our company.the software(p6.2) is installed in one of the computer which has the following configuration. ram 3 GB HARD DISK SPACE 160GB PROCESSOR SPEED 2.2GHZ...

Apr 10, 2011

p6 version 7 server

Forum Topic

Dear ALL I have aquery if we have for example aproject contain 60 buildings and 6 areas ,every area include 10 buildings assume that 6 planners work in this project ,the planner will update for one area. how the planners work with each others and org...

Apr 10, 2011

Shut Down Activities

Forum Topic

Any one have asample schedule dor shut down project please send me

Apr 10, 2011

Rain Delay and Concurrency Issues

Forum Topic

Dear PP friends, I would like to hear from the community your point of views about the effect of awarded rain delay days and concurrency. It is common practice at home for the rain delay be awarded on some rule as to the amount of hours you could wor...

Apr 10, 2011