Dear ALL
I have aquery if we have for example aproject contain 60 buildings and 6 areas ,every area include 10 buildings assume that 6 planners work in this project ,the planner will update for one area.
how the planners work with each others and organize the work in the same time via server in p6 version 7 ?????
Ahmed,
several planners will be able to work on the same project plan at the same time; they cannot edit the same activity at the same time; they should be carefull not to work in the same part of the project alltogether, not to spoil the project plan
as Primavera saves the data by itself when the user enters new data in the project plan, no problem about who will save the project the latest.
Alexandre