Budgeted cost extends beyond the project finish date.
Forum TopicHi everybody I have a problem with one of my program (Updated Program), I want to use it as a revised baseline. The issue is project finish date is 24-Jan-2019, but when i check the activity usage spreadsheet, Cost loaded in the Preliminarie...