Interactive Planning Session Question

A few times a month, I facilitate interactive planning sessions between owners and subcontracted engineers and constructors. Normally ill print out a big paper timeline, hadwrite activity descriptions on post it notes and positon them on the timeline before the meeting starts. During the course of the discussion, we'll move the post it notes around to create our baseline plan. After the meeting, I'll input the information into P6 with logic, durations, and resources. At that point our baseline schedeule is created.

 

To me it seems a little unprofessional to handwrite on post it notes, but that's the standard at the company I'm working for. Is there a better way to do this? Does anyone have any tips on how to make an interactive planning session more efficent?

 

Thanks in advance!

S
Santosh Bhat 👤 Member for 21 years 1 month

Use a more collaborative Planning and scheduling tool like Netpoint by PMA Technologies.

M
Mike Testro 👤 Member for 20 years 5 months

Hi Ryan

You are describing the "Lean Planning" process which has its use except that you have to do it all over again the next week because nobody actually pays any attention to what the planner says.

BTW you forgot to mention the pins and string.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts