Critical Path
Forum TopicAny expert, please help me out. What is the best way to get only one critical path in P6 rather than getting 2 critical paths in the same programme ?Cheers,Andy
Any expert, please help me out. What is the best way to get only one critical path in P6 rather than getting 2 critical paths in the same programme ?Cheers,Andy
Hi I am new in Primavera P6 version R15.1When I was assiging cost to resources that I created, I couldn't find the Price/Unit column to assign the cost in, I just found Price/Unit4 and Price/Unit5 which they didn't work in further steps in the progra...
Hi Everyone.I'm currently working on a Revised Program from the last update (in P6), and I've already adjusted and Corrected all dates and Relationships and even I've used Global Change to make Planned % Complete and Actual Percentage complete equal,...
Here's a quick tip for how to specify calendar non-work time while accessing one or more Primavera P6 EPPM release 16.1 project schedules http://ed.gr/c81k
Hi,Please see attached screeenshot (http://ge.tt/7uuG97m2 ). . I previously used it in Asta.Now I need your help to do so in P6: a) How to give Weekly planned % complete column and actual Weekly % Complete column as I highlighled in rectangle?b)Ho...
I cannot get P6 to show work across both shifts in my resource profile despite the schedule shoing correctly as a 24h operation.I thought it must be a settings issue so compared all settings against my colleagues and they all match with his working f...
I know a person who is a project manager. I don't know much about it myself, I was wondering what are some common mistakes, and mishaps in project management?
In resources, max units per time means i have to add duration of particular material or machinaries in day or nos of material set or machinaries we are using in a day. Example, If I am using 4 Hydra then when I am inserting hydra as a resource then...
How do I display the key for trades from code libraries in the printed border?
Forum MembersHopefully someone can point me in the correct direction here.I have 7 data points (actuals from a mini-project i'm currently doing - 2800, 4300, 8300, 11000, 13600, 14900, 17400) and would like to trend these out to week 26 to give me a ...
Does this mean these the software can level consumable resources, or they just make a warning of some over allocation?Oracle Primavera P6:Adding Resources - Use this task to add resources to the resource pool. Resources include the personnel and equi...
Distinguished Planners, PM,Please i have issues measuring the progress with Ordered and delivered material. I built in every material in my program but the performance % complete keps reading zero wheni filter for procurement. How can i deal with thi...
Hey everyone, I want to take a planning & primavera course and was wondering if someone can help me with the following questions: 1. What is the 102 course ? 2. Is it better to have an online course or a classroom based course? Thanks in advance !
Hello all,Wanted to ask if the planners on this forum follow any specific colour scheme on a programme?Just curious to know if you use a standard colour scheme on all propgrammes you use or have different pallettes for different programmes.This would...
Morning all,I have a project with external links to a suppliers project. well I have two to be honest.On one of them if they change the project number I lose the links and on the other I do not.My settings are all the same and I can't see any differ...
Hi ,I have some issues,I need to use Expense Cost and Man-hour related progress. I want to see the Planned progress and Actual progress based on the Expense Cost and Man-hour same time.I believe we can load Expense Cost as well as Man-hours to the Sc...
Here's how you can employ the WBS Summary activity to list top down estimates beside bottom up estimates in http://ed.gr/dhje
Issue with P6 showing over allocation to things under the limit (see pic). These are multiple resources combined. Why is it showing over allocation when the resources are under the limit? Any help would be great. [[wysiwyg_imageupload:4951:]]
I m trying to review the MS schedule submitted by the Contractor, i noticed that he is changing the activity links and lags in the updated monthly schedule, does anyone have a spreadsheet or a certain method to review the links I tried exporting the ...
Hi I hope this has been posted in the right place...I have a situation where a contractor has had a clause 31 programme accepted however from day one the construction team are undertaking works in a different sequence... they clause 32 is due in 3 we...