Revised Program in P6

Hi Everyone.

I'm currently working on a Revised Program from the last update (in P6), and I've already adjusted and Corrected all dates and Relationships and even I've used Global Change to make Planned % Complete and Actual Percentage complete equal, it worked well for Enginerring, Procurement and Even Construction Stages, but 3 activities (2 from Pre-Construction Documentation and 1 key milestones (Contract period)) didn't change, which is affecting Overall % because the 3 actiities are being update using Physical % Complete, and if I change them to duration % complete it is affecting their actuals, which is affecting Overall % also (driving it back).......

 

Please how do I solve this kind of Issue withouth Changing it's % complete type to Duration??????

 

Thanks & Best Rgards.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

run a global change

where physical % complete is greater than 0

then duration % complete = physcial % complete

have you copied this schedule and made this your new baseline ?

what is your earned value calculation setting ?

Budgeted values with current dates

At completion values with current dates 

Budgeted values with planned dates

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts