Modeling Cure Time in Microsoft Project
Forum TopicHere's how to model cure time as a separate task using standard hours and a 7-day work week http://ed.gr/cxo9
Here's how to model cure time as a separate task using standard hours and a 7-day work week http://ed.gr/cxo9
Hi all,I am using ASTA version 14 and I am trying to figure a way around something which might be very simple.When I open an old file say from a year ago to just have a look at and then close the file, the software seems to change the "Date Modified"...
Hi,Any suggestion on where to find a well-detailed explanation of how the lag between different activities in P6 are scheduled?I am experiencing some strange behaviors in particular cases, for which I am not able to provide a rational explanation.e.g...
I am involving in a planning of turnkey Substatiin construction in India.It is completely new field to me.Can any ine suggest with the sequence of activities which is normally used.If possible any sample schedule of it to get overall idea.
Hi guys,I have a problem with my p6.I am done with my planning and I want to put my new data for the next month manually;*First problem=When I click the start box in status bar and change the data with a different date finish box doesn't change auto...
CHĂM LO CHO SỨC KHỎE CỦA MẸ!Điều được nhắc đến nhiều nhất trong tình cảm mẹ dành cho mỗi người con hẳn là tình yêu bao la trong lòng mẹ. Khoảnh khắc bé yêu chào đời, cuộc sống của mẹ như có thêm vô vàn màu sắc. Để chuẩn bị cho điều ấy, sức khỏe của ...
Can anyone tell me how I show the baseline programme on an import from Asta Powerproject?I have converted it across from Asta and it's displayong the as-built but not the baseline. Is there any way to show this on the converted programme? Also it loo...
Hello guys It's the last day of the month and I have been assigned couple of projects to update, I have updated most of it but I have 2 projects left to update. One of this projects already have 9 days delay with a terminal float duration of 6 days. ...
Projects are immense endeavors and as a project director or manager you realize that projects include dangers and imparting those dangers is an exceptional ability.What Makes Project Risks Hard to Communicate?
Hi,Need Some Expertise on Engineering Planning for a Small Refinery Project Let say 1000 Equipments:1. How many total Engineering manhours Should be Estimated based on Number of Equipments ?2. How long the Engineering Will go to give Sufficient Front...
decent SOV and Submittal Package tracking software, even better integrates with P6, ebuilder, etc. - I still just see excel used even on giant jobs, there has to be a better way. I have been investigating...most I have found are a small afterthou...
Hi there!I am currently facing this issue wherein when I import a program into another computer the late start and late finish dates change. So technically my entire float is changing.Any reasons why it might be so? I checked the calendar. It is same...
Why we prefer to use Nonlabor resource in BOQ loading on the schedule instead of labor and material resource?
Hi everyone,I am working on a system running MSSQL and P6 EPPM v15.2.Trying to import a schedule backup in XML form with baseline into the database through P6 client.SEVERE: DBEngine.executeUpdate: Violation of PRIMARY KEY constraint 'pk_trsrcfin'. C...
Hello there!I am having issues while importing units and durations on P6, using XLSX files. When I import floating point values, it ignores the decimal point and import as an integer. For example, importing 12.05 and it writes 1,205 in the database. ...
I've Oracle Primavera P6 Professional R16.2Project WBS contains 10 Major Items (Sites)Contractor send update, I assign Baseline for compare Schd % against Perf %the problem is, one of the sites' Performance % Complete Changes after I assign the Basel...
I need a document detail explanation about the benefit and implementation of tracking window primavera p6. But I search a lot could not finding not find everything in detail regarding tracking window ond tracking layouts.down votefavorite
Hi allplease assist me in the following matter:A recent project has been the subject of numerous (approx 300No.) notifications of potential delay and 25No. actual EOT claim submissions by the Contractor. These have largely been rejected by the princi...
I am curious if anyone is experiencing this issue. I can export a .xlsx from P6 R16.2. I can open the file just fine in Excel . However, if I save it in Excel without making any changes and try to import it into P6 R16.2, I get this error: "The User...
Hi all!It would be greatly appreciated if you could take the time to answer our survey on sustainablility in project management. Thank you!https://bino.qualtrics.com/jfe/form/SV_eeWB8yV7rRyTGoB