9days delayed

A
Ahmed Sho 👤 Member for 8 years 1 month

Hello guys
It's the last day of the month and I have been assigned couple of projects to update, I have updated most of it but I have 2 projects left to update. One of this projects already have 9 days delay with a terminal float duration of 6 days. Please can anyone help me of how to update this delayed projects...Thanks

M
Mike Testro 👤 Member for 20 years 5 months

Hi Ahmed.
Remove the end constraint flag and let the logic run free.
Best regards
Mike T.