I’m hoping that someone can help with the following…. Has anyone managed to use the Site Progress Mobile App from Asta successfully? Can the data be backed up to local server instead of using an iCloud? Is there other methods used that can have a cop...
I am new to planning and am trying to understand link logic and am getting very confused. I have only used finish to start links or finish to finish. Can you please tell me why have a start to finish and what does it do different to a finish to start...
hicould any one tell me how to update the budgeted uniti have assigned material resource to an acitivity and when am updating both physical and duration % complete works fine but not unit complete %
Hello, I'm working in a project that has contractual certain dates for submissions of documents. How should I link these activities? Especially, if I figure that I can send these documents earlier than the contract date according to program but I don...
Mix summary and detail bar description names - without a jumbled typo line next to the summary bars. I guess I could create a custom column and have it blank for WBS items that I will roll-up but I assume there should be a way without the extra step...
Hi experts, How long does it take you to develop your construction work programme on P6 for such a project: - An advanced Finishing works (Finishes and MEP) for a hospital - detailed construction schedule (duration must be less than 16 days for any c...
Hi allI wonder if you can help me? I have recently started a new project, which is a bespoke design. There are many prototypes to be designed and manufactured. These prototypes will tested against eachother and further design will be required unti...
I need to put the week numbers against activities. ie act 1 starts on the 2nd June. On the calendar I have set 2nd June as week one. How do I have that next the start date of the activity - same with the finish date. Act Start Wk No...
Dear planners,I reschedualed my project, the new finish data change when I update project to compute planning progress percentage. how can I update rescheduled project in MSP. Regards,Hasanzadeh
Good evening all you P6 experts.How can i create a filter on a specific UTID.I have a delay analysis programme with an Event that has a UTID - 0123 ABCDefg and a task UTID ABCDefg.In Asta powerproject I just set up a filter which says UTID *ABCDefg* ...
Hi Folks, Doesn any one know how to run schedule health-check after updating schedule for %complete/atcual cost on a weekly basis in EPC and FEED? Neda
Hi,If we want to use oracle database for Primavera, how many license we need?For example, we buy 3 Primavera license, how many database license we need? It is 3 or 1. And what type of Oracle database we should buy? I see there are 4 type:Oracle Datab...
WBS has 3 dimensions, and the OBS is added. But there are also "dynamic" dimensions.It looks like that: http://3d-wbs.blogspot.fr/2014/06/part-120-tetrahedron-projects-like.html
Project portfolios, projects, sub projects, tasks = same fight ! http://3d-wbs.blogspot.fr/2014/06/part-121-project-breakdown-as-fractals.html
Hi fellow applicants.I have been taking some time exploring the guild application process for Fellow (Black Belt) level at delay analysis.I have found it to be a mares nest of interlocking websites that take you to no clear destination - unless it is...
Here's a great tip on how to add ad-hoc Activity Codes in Primavera P6 http://ow.ly/xV2vW
dears, is it possible to hide the WBS summary activity bar, but it still need to show the WBS summary activity, please advise me. tank for your help Jason
I have prepared a Baseline in P6 but it is not approved due to several comments. The Main comment which is making problem for me is float. My activities has float over 200 and client instructed do not exceed total float than 80. All milestone activi...
in my schedule there is an activity B which has a successor of G with SS. B and G is critical but another activity C which follows B by FS starts one day after B is finished because of another relation. So B start can not move and this makes b critic...