Mike Testro 👤 Member for 20 years 6 months

Good evening all you P6 experts.

How can i create a filter on a specific UTID.

I have a delay analysis programme with an Event that has a UTID - 0123 ABCDefg and a task UTID ABCDefg.

In Asta powerproject I just set up a filter which says UTID *ABCDefg* and both tasks come up making it very easy to link them FS.

How do I o this in P6.

Best regards

Mike Testro

M
Mike Testro 👤 Member for 20 years 6 months

Hi Gary

Simple when you know how - I was looking for UTID not knowing that in P6 I should be looking for Activity ID.

Best regards

Mike Testro

G
Gary Whitehead 👤 Member for 17 years 2 months

Pretty much in exactly the same way: set up a filter with Activity ID contains "ABCDefg"

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts