52R-06: Prospective Time Impact Analysis process diagram Step 8
Forum TopicI have a little bit of confusion for understanding the step 8 of this recommended practice, can anyone help?
I have a little bit of confusion for understanding the step 8 of this recommended practice, can anyone help?
Hello Planners!I need advice to understanding Remaining / Actual / At Complete Units calculation. There is 40hrs long activity to which a labor resource is assigned with 40h budgeted units. Calendar is 5d x 8hr. When activity started and DD moved 1 d...
Hi everyone,In my turnaround project, I chose the percent completed type is physical percent completed, but the problem I faced was that percent can not show at WBS or total bar as well. Can you advise me how slove this problem?Thanks alot.Viet Tran.
Hi,[[wysiwyg_imageupload:6697:]]I have an activity in my schedule that has a Budget At Completion=PV=EV=$16,451.87, while my At Completion Total Cost for that activity= $66,084.98 (as in the attached screenshot).The Baseline was snapped two months af...
Hi guys, if your Contract Specifications require Oracle (Primavera) P6 programming, please consider CPM Specialist. Please check the website:www.cpmspecialist.co.uk
How do I copy activities from P6 project plan to another P6 project plan, how do I copy and paste
Hello everyone,I have a question; Is it possible to import columns with (*) to P6? I mean columns such as "Physical % Complete" or "Budgeted labor unit".Thanks in advance
Hello,I recently upgraded to Oracle Primavera Professional version 18.8 and now I am unable to import P6 XML files or Microsoft Project XML files. This happens for both a MSSQL database and SQLite database.Also, I went to the Oracle website https://e...
Using the agents laptop with v 8.2 for several months now and today it would not start.The error message says Primavera P6 Professional R8.2 has stopped working.A problem caused the program to stop working correctly. Windows will close the program an...
Good Afternoon,I have re-visited some cost loading bars in the programme and split them out in order for the commerical team to accurately represent the cost spread.The actual start date for the cost bars is in the past, i.e. before the data date and...
Here is the usual VBA code for looping through all tasks in a project: For Each t In ActiveProject.Task {code for desired action} Next tThis loops through from the top down (as far as I can tell).Anyone have an ideas as to how I can reverse t...
Is there a method to capture and report the work that had been progressed or completed in the last reporting period. Using a filter i created finish date is in the range of DD-7days to DD which will show all work completed. But some of the tasks ...
it is just a blog post on how to recreate look ahead filters in PowerBI https://datamonkeysite.com/2019/05/04/using-or-conditions-between-slicers-to-filter-primavera-schedule-using-dax/ hope you find it usefull CheersMim
Hi,I just started my job as a junior project manager but, I have a question to you - more experienced PMs. What are your main Pain Points in your daily work and how do you handle them?Thank you for your answers!
Hi ... How to deal with "Out of sequences / Hangers" while tracking the project? I know how to find, but i just want to know how to fix it without changing the baseline end date?Please note, ours a simple duration tracking project, without any resour...
Hello Folks ,Just need to ask about UDF removal / hide- We are having lots of UDFs which are not using from long time but consuming lots of data. Is there any way we can filter out which udf is not in use so that we can remove the UDF. Also need to ...
Hello Folks ,Just need to ask about UDF removal / hide- We are having lots of UDFs which are not using from long time but consuming lots of data. Is there any way we can filter out which udf is not in use so that we can remove the UDF. Also need to ...
A couple of weeks ago I couldn't open my 8.2 stand alone P6 on the laptop loaned to me by the consultancy that I am contracting through. Didn't get any help and got the problem fixed by taking the laptop to a local repairer who deleted quite a few vi...
Is there any way in primavera that I can recall that information?I took over from a previous plan and now they want to improve in the past. for example, they want early start costs and late start costs for a specific day in the past.
I've recently been charged with revising and maintaining a relatively substantial schedule (700+ tasks) for a client of the company I work for. This is the first time I've delved into scheduling, and it's definitiely trial by fire here, so please bar...