Baseline assigning Error

Forum Topic

I am using Primavera P6 ver 15.2. I imported a schedule into a clean database and tried to assign a copy of schedule to itself as a baseline. A message puped up that "job has been schedules. See job statuse for more detail" Does anyone know what the ...

Sep 19, 2016

P6 Team Member- unable to view Start and Finish Time Hour and Minutes

Forum Topic

Dear All, Has anybody encountered the issue of not being able to view Time Hr:Min using Primaver p6 TeamMember App. I am unable to view Start and Finish Time (Hours and Minutes) of an activity on P6 Team Member App. I have attached a screenshot with ...

Sep 19, 2016

Resource Assigning

Forum Topic

Usually, Project manager or Site Safety are on site from the start of project. we make a resource for Project manager. how can we assign this resource to activiteis? should i add it for all activiteis?  

Sep 20, 2016

Issue with upgrade

Forum Topic

Dear All,I encountered this issue while trying to upgrade from P6 to P8.2 on system 1 using the same software I installed successfully on system 2, even though I had purged the former of all files relating to primavera.[[wysiwyg_imageupload::]] Not s...

Sep 20, 2016

Sub Contractor and small Contractors ONLY

Forum Topic

If you are in delay and being treated unfairly by a Main Contractor or Employer and can't afford adjudication then I can help. No upfront fee for a case study and assessment of your position. email [email protected] for further details.

Sep 20, 2016

P6 Filtering on Activities View by Resource?

Forum Topic

Good afternoon all,I'm trying to pull together an engineering specfic layout with EV info and have hit a stumbling block with filtering.What I am trying to do is only show activities with a certain set of resources assigned, plus filter to only show ...

Sep 20, 2016

Progress Update - Restatus

Forum Topic

Respected Engr's,For an ongoing project, with duration completion of 4month, the Lead Consultant (A) was suddenly changed to another Consultancy (B). Now, the issues is during those 3 months, whatsoever the Engineering Submittals i.e. Prequalificatio...

Sep 21, 2016

Wanted software all in one Project, Task , Time Manangement

Forum Topic

Hi all.  Looking for software which include all in one Project management + Task Management + Time Manangement. May be it Task Management + Time Manangement fully integrated with Microsoft project. This software will plan to use in big company with l...

Sep 21, 2016

Cost Loading at Late Stage of Project

Forum Topic

Hi all,I was just asked to cost load P6 for a project that has been running already for 3 years..30,000+ activities..I started by assigning in a cash resource the remaining $ (Contract BOQ $ - Actual to Date $) for each activity and the % is calculat...

Sep 21, 2016

Resource load levelling within multiple projects

Forum Topic

Hi all,I have a query relating to load levelling resources within multiple projects with differing priorities.I know a project has a "Project Levelling Priority" function within P6, so you can level using "Level Resources" that way; however, my sched...

Sep 21, 2016

How can I see planned AND remaining work in the same report?

Forum Topic

If I am running a cost loading report out of a status project, for the purposes to inform my customer what unfinished work is remaining on the project, and how it is time phased, I am only seeing BCWS.  The remaining work of the in progress activitie...

Sep 21, 2016

Resource usage profile chart not displaying correctly?

Forum Topic

Dear all,sorry i am newbie in P6 and just doing some self study.i am having some prblems with regards displaying the actual resouces used in my project. i have assigned the planned and actual resources on each activity but when looking ant the resour...

Sep 22, 2016

planning engineer - other name

Forum Topic

Hi,Am currently working as a junior planning engineer in UAE, I plan to immigrate canada. I just went through the job bank of canada, I could not find the job posts for planning engineer.I need to know is there any other name for planning engineer?

Sep 22, 2016

planning engineer - other name

Forum Topic

Hi,Am currently working as a junior planning engineer in UAE, I plan to immigrate canada. I just went through the job bank of canada, I could not find the job posts for planning engineer.I need to know is there any other name for planning engineer?

Sep 22, 2016

Resource leveling in PRA

Forum Topic

Hello planners,Where could I find some comprehensive documentation about the nudge and resource leveling process in Primavera Risk Analysis?Having tried to level the same project in P6, MS Project, Spider and finally PRA, I find that PRA does not res...

Sep 22, 2016

Activity Delay in p6

Forum Topic

Hi every onecan  Actrivitiy Has a delay in days more than the Updating interval ex.: if th update Int.=30daysafter update can the activity has more than 30 days delay greater than the previous delay ???

Sep 22, 2016

Tracing Activity in HUGE Project

Forum Topic

I work with a P6 Portfolio that has over 36000 activities in it. What I am struggling to do is determine if activity "A" is associated with activity "Z" because there are sometimes 500+ predecessor/successor activities and the Trace Logic tool is cum...

Sep 22, 2016

Tracing Activity in HUGE Project

Forum Topic

I work with a P6 Portfolio that has over 36000 activities in it. What I am struggling to do is determine if activity "A" is associated with activity "Z" because there are sometimes 500+ predecessor/successor activities and the Trace Logic tool is cum...

Sep 22, 2016