Search

Procurement Schedule Weights

Forum Topic

Hi All,I am presently working on preparation of overall EPC schedule. I want to add weights to procurement activities like:. PO Placement. Vendor doc. approval. Manufacturing. Inspection. Ex Works I can calculate weights as per total equipment cost b...

Nov 25, 2016

Construction tolerances

Forum Topic

Dear, My problem, in fact , is not related to project management,, but it seems that I couldn't find appropriate area to discuss and that is why I would like to post here for discussion.It is ususally that there are tolerance for individual structura...

Nov 28, 2016

P6 16.2 Import Problem

Forum Topic

Hi All, I have a problem about importing my actual dates to primaveraWhen I selected my excel sheet to import Primavera, P6 notice me thatThe User Preferences used to create this Excel file are not same as your current preferences. Importing this fil...

Nov 28, 2016

Hide Summary %complete

Forum Topic

Hi,I'm looking for a way to keep hide the summary % complete in the percente complete field.ThanksAntonino

Nov 28, 2016

Period Performance

Forum Topic

Hi ive been asked to put in some costs for one of our projects.the month of november has costs of £18.31 so i status the activity and update to next data date. after data date i store period performance so £18.31 shows on resource assignement tab and...

Nov 29, 2016

Project planning for new product Introduction

Forum Topic

I have got below assignment.Create Project Plan for introduction of new product. • Project Plan must encompass all aspects of project from design to launch. Rough Time scales • Product leadtime – 12 weeks • Production time – 2 weeks Note: Accuracy of...

Nov 30, 2016

Units but No Cost

Forum Topic

Activity has units stored in November 2015 of -70000 (but no value in the cost) but is finshed in December 2015 then in the September of 2016 the same activity has units of +70000 (but no cost).if i try to zero the period it just causes the units to ...

Nov 30, 2016

What is the most impressive piece of planning in history?

Forum Topic

What do you think is the most impressive piece of planning in history, in terms of the complexity of the task and successful outcome. Was it Operation Overlord,(D-Day), the Manhattan Project, the Apollo Program, the LHC or something else? This seemed...

Dec 1, 2016

P6 Print function turned off?

Forum Topic

I'm using P6 version 6.2.1 and I'm encountering something I've never seen before. The print, print preview, and page setup functions are all grayed out. I suspect this is a user rights issue, though I've looked and can't see anything obvious. I don't...

Dec 1, 2016

Planning Identification

Forum Topic

What's name of that planning where Planner puts adhesive/sticky different colour notes in conference/meeting room wall/board to show 4/2 weeks forthcoming/lookhead dates for weekly meeting with Site Team, Subcintracor or Design team etc.Regards,

Dec 1, 2016

Help Understanding Resource Allocation

Forum Topic

Happy first planning planet post to me.. :)Hope you guys can help. So I have a schedule in Microsoft Project 2007 and I have a "General Project Management" task which has x amount of hours allocated to it a 1 resource. That task is linked up to the s...

Dec 2, 2016

Delay Analysis in P6

Forum Topic

Gents,Can you please let me know, how easily i can define the dependencies in P6, in order to show the delay events.  Cheers,Regards,Zaid

Dec 4, 2016

planning units

Forum Topic

dear all,i created resource excavation budget is 22965 m3 at the beginning of the project & this budget by p6 divided as follows aug. 21872, at Oct. 608 & Nov. 216.which is not appropriate for the project so i need to adjust it manual per month on P6...

Dec 6, 2016