Open a program in p6.4 with a release p6.3

A
Ant Pir 👤 Member for 12 years 11 months

Hi,

Somone kow the procedure how open a program saved p6.4  with  a release p6.3

Regards

Z
Zoltan Palffy 👤 Member for 16 years 11 months

go to windows explorer

highlight the xer file 

right click and select open with then choose note pad or word pad

in the first line of the file chnage the numbers from 6.4 to 6.3

save file

import file