Project total negative float is less (in absolut value) than some activities' negative float
Forum TopicHi everyone, I'm using P3 and have a 4500 activities schedule. The problem I'm facing is the following: The total float of the last activitiy of the project is -10 days, and I have within the program activities with -15 days of total float. I thought...