Search

Man Power Histogram

Forum Topic

Dear AllCurrently I am handling a project having a one month delay ,I want to prepare man power histogram , The histogram i prepared is based on Baseline and now it is not reflecting the exact   situation of site due to delay1. Is it possible tp prep...

Jun 18, 2012

Critical Activities

Forum Topic

Dear Planners,I am producing time scheduling for Pipe manufacturing, it is production line and the schedule is EPC (Eng. Procurement and Construction) the size of critical is massive as most of the activities are critical, is this right?Regards,Mouta...

Jun 18, 2012

PM6 level resource

Forum Topic

Hi, Can Primavera (P6V7.0) level ident (parent/children) resource? Per example: Resource level 1: Unit maximum manhours; 50h/h Resource level 2: Electrician maximum manhours; 20h/h Resource level 2: Welder maximum manhours; 40h/h Resource level 2: pi...

Jun 18, 2012

Cumulative late curve

Forum Topic

Dear All, How can we generate a cumulative late curve from the resource usage spread sheet in P6. Your valuable remarks are highly acceptable.. Regards. Sunil.

Jun 19, 2012

Resource Lag

Forum Topic

Hi guys, How do I put a lag in a specific resource? Example is I have an activity with 10 day duration. A resource will be introduced half-way (after 5 days) up to completion of that activity. In P3 it was very simple. How about in P6? Thanks.

Jun 19, 2012

Merging Multiple projects into one project

Forum Topic

Hi;I have got separate schedule for Procurement,mobilization and construction from our sub-contractors.How to make these all as one project? Regards

Jun 19, 2012

Organogram in P6

Forum Topic

Hi ,I have one question...In P6 , lets suppose i have multiple projects , Every project has its own organizational hierarchy (OBS)..... and for example i select one project and only want to take out the print of this projects hierarchy (not all) ... ...

Jun 20, 2012

Original duration change during Import.

Forum Topic

Dear All, Why original duration changed when I import XER file and be not matching the start and finish date? I mean start and finish date show only five days but the original duration show 1 day. Thank you, HANSON 

Jun 20, 2012

P6 Progress Drop-Line

Forum Topic

Hi All i am wondering if its possible to create progress dropline on Release: 6.2.1. Thanks

Jun 20, 2012

New Primavera P6 video tutorial covering Claim Digger

Forum Topic

Hey everyone! Here is a link to our latest Primavera P6 video tutorial covering Claim Digger. It can be found in our website's Primavera software training blog or by following the link : http://mssprojectsanalytics.com/blog/bid/172152/Primavera-P6-Tr...

Jun 20, 2012

remaining / at completion duration

Forum Topic

Dear all, please help me with the questions below, thank you. 1. When i status my schedule, i notice that sometimes when i check the status of an newly started work as "start", the duration in "at completion" row will change to a duration longer than...

Jun 20, 2012

How to see (explore) the source of linked field.

Forum Topic

 I am just playing around with Linked fields in Ms project (Paste Special => Paste Link). This seems to be quite a powerful feature especially taking into account, that one can link both within file as well as even to outside file (e.g. even to Excel...

Jun 20, 2012

Claim Digger problem

Forum Topic

Hi All,I want to use claim digger but failed so far. When i open it and click the "select revised project" then at that moment only few projects appear in the dorp down list and i cannot see the full list. why is it so?. How to get the pop in of full...

Jun 21, 2012

Claim Digger problem

Forum Topic

Hi All,I want to use claim digger but failed so far. When i open it and click the "select revised project" then at that moment only few projects appear in the dorp down list and i cannot see the full list. why is it so?. How to get the pop in of full...

Jun 21, 2012

When copying WBS element the Activities are not copying?

Forum Topic

Hi Forum,   I have opened up two projects together in P6 and have been copying WBS elements in the WBS window from one project and pasting them into the other. This pasted WBS levels and activities into the second project. All the sudden when I copy ...

Jun 21, 2012

Man Power Histogram from actuals

Forum Topic

Dear all I prepared a man power histogram from actual dates ( actual start and expected date to finish ). there are activities alredy started and compleated 50% and consumed 50 % of man power, but the generated man power histogram  not showing any  r...

Jun 21, 2012

Re-schedule

Forum Topic

After I press F9 to re-schedule a box appears on the screen, asking what date to straighten the progress line to. I turned that box off, and now I want to turn it on again. How do I do this ?? Thanks  Ronan

Jun 21, 2012

Suretrak downloading

Forum Topic

Hello Everybody,i have got native files of Suretrak, but cant open it. i tried to download it from internet, but cant do that. Could anybody help me with that? Thanks beforehandIsmayil

Jun 21, 2012

Planned % Complete vs. Actual % complete

Forum Topic

Is there a way in P6 to show in column fields the Planned % complete of an activity versus the actual % complete of the activity?  I have a baseline of the schedule, but I do not see a column in the Percent field listing to use for Planned % Complete...

Jun 21, 2012