Hi,
Can Primavera (P6V7.0) level ident (parent/children) resource? Per example:
Resource level 1: Unit maximum manhours; 50h/h
Resource level 2: Electrician maximum manhours; 20h/h
Resource level 2: Welder maximum manhours; 40h/h
Resource level 2: pipe fitter maximum manhours; 20h/h
As the sum of Resource level 2 (20+40+20=60h/h) is greater than Resource level 1 (50h/h), I want PM6 consider both level. It is possible?

Regards,
Yannick
Thanks,
Finally, we created a material resource call "area". The resource "area" have the same amount of unit then the human resource. So, the levelling is done on both resource and we respect the maximum of resource by trade and by surface area.
Regards,
I suggest to create dummy resource worker and assign the same number electricians and workers, welders and workers, pipe fitters and workers.
Then you can level workers and this is the same as add another level.