PM6 level resource

Hi,

Can Primavera (P6V7.0) level ident (parent/children) resource? Per example:

Resource level 1: Unit maximum manhours; 50h/h

Resource level 2: Electrician maximum manhours; 20h/h

Resource level 2: Welder maximum manhours; 40h/h

Resource level 2: pipe fitter maximum manhours; 20h/h

As the sum of Resource level 2 (20+40+20=60h/h) is greater than Resource level 1 (50h/h), I want PM6 consider both level. It is possible?

capture.jpg

Regards,

Yannick

Y
yannick pilon 👤 Member for 14 years 4 months

Thanks,

Finally, we created a material resource call "area". The resource "area" have the same amount of unit then the human resource. So, the levelling is done on both resource and we respect the maximum of resource by trade and by surface area.

Regards,

V
Vladimir Liberzon 👤 Member for 25 years 4 months

I suggest to create dummy resource worker and assign the same number electricians and workers, welders and workers, pipe fitters and workers.

Then you can level workers and this is the same as add another level.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts