Resource Usage Profile Option - Unit Of Measure

Forum Topic

Hai How can we Show in Resource Usage profile Option Unit of Measure As Nos. I did it in Following Way Eg I Created One Resource Carpenter  Resource Type - Labour Unit of Measure As - Nos Edit-> User Preference ->Times->unit Format-> Day After That I...

Jan 10, 2011

Resource Usage Profile Option - Unit Of Measure

Forum Topic

Hai How can we Show in Resource Usage profile Option Unit of Measure As Nos. I did it in Following Way Eg I Created One Resource Carpenter  Resource Type - Labour Unit of Measure As - Nos Edit-> User Preference ->Times->unit Format-> Day After That I...

Jan 10, 2011

Man-Hours

Forum Topic

One “man-hour” is one hour of one worker. If one worker can pour one 1 m3 concrete in 15 hours, then 1 m3 can poured in 15 man-hours. Theoretically, with three workers working, one m3 conrete can be poured in five hours. Spent Man-hour Spent man-hour...

Jan 10, 2011

Performance Factor (What do you use?)

Forum Topic

Dear planners;   As you know, for performance factor tracking we all use unit planned man hours. What i always do is; at the beginning of the project i forecast unit manhour for activity and i update it next forecast (in 3 months period). For exampe,...

Jan 10, 2011

Baseline and Update bar

Forum Topic

Dear Planners, Why the baseline and update bar are coincided "identical" for the non started activities?   Regards,   Moutaz

Jan 10, 2011

Can Main Contractor Insist For A Specific Delay Analysis Method ?

Forum Topic

One Year Sub Contracts WorksFinish Date as Per Contract: 31 Dec 2010Main Contractor Cleared Just 60 % of Area so far , For Sub Contractor worksComplete clearance likely  to take 6 more monthsSub Contractor Asked for EOT, Submitted EOT Claim based on ...

Jan 10, 2011

Getting the hours out of P6

Forum Topic

Hi   This is simple stuff but I seem to have fogotten and cant find anything in the forum  giving exactly the info I need. I'm pretty new to P6 resources and have a loaded schedule per discipline and I want to take the hours out to produce an S curve...

Jan 10, 2011

Master Schedule for Offshore Windfarm Projects

Forum Topic

Hello Members, Can someone share with me a copy of project schedule for offshore windfarm projects please. Here is my email address: use private messaging service Regards, Amanullah  

Jan 10, 2011

Direct & Indirect Crew? Who are they??

Forum Topic

Dear Planners,   As i know and i use, direct crew is the person who is directly giving progress to activity (carpenter doing formwork, rebar crew, piping crew etc). and indirect crew is person who is helping that activity (to direct crew) to give pro...

Jan 11, 2011

Relationships Help required

Forum Topic

Hi there, I wonder if someone could remind me how I could sort this out? I have 5 activities A, B, C, D & E starting at different times from now until April, I have them all linked into another activity (F)which I need to start with the earliest date...

Jan 11, 2011

Upgrade from p6 to p6.2.1

Forum Topic

Dear all, Please advise me how to upgrade my Primavera P6.0 to P6.2.1..? Now i am using P6.0 standalone in my system.. Thanks in advance.. SHIVA

Jan 11, 2011

EV Reporting Ethics

Forum Topic

Im working in an integrated project team which contains client employed engineers and a difference between commercial and government employees is becoming apparent... When reporting Earned Value, is the performance you report at the discretion of the...

Jan 11, 2011

Schedulling Problem in Primavera v6.7

Forum Topic

Dear All, I am facing a problem while scheduling in Primavera v6.7 as following: The start date of a successor activity is same as the end date of the predecessor activity.  The start time of some activities is 7:00am which is the start of the day as...

Jan 11, 2011

Problems in P6 schduling

Forum Topic

 Dear All,I am facing a problem while scheduling in Primavera v6.7 as following:The start date of a successor activity is same as the end date of the predecessor activity. The start time of some activities is 7:00am which is the start of the day as s...

Jan 11, 2011

Retail Building Construction Schedule?

Forum Topic

Hello,   Can someone please steer me to the schedule repository or send me a retail building construction schedule template.   Thanks, Tom   please use the private message service

Jan 11, 2011

Russian Text in a user text field

Forum Topic

Hi guys.  I am trying to add Russian text in to a user defined field.  My copy of P6 dose not allow the cyrillic charecters. I have added the language to the reginal settings but When typing into P6 it typs a gibberish font. Can anyone help?   thanks...

Jan 11, 2011

P6 - Resource Driven Activities

Forum Topic

Can anyone tell me what happens, if you tick the box, 'Drive activity dates by default' on the Resource Tap on the Project screen when in the Enterprise View? We are using resources. 

Jan 11, 2011

Use of Delay Allowances, Buffers etc

Forum Topic

I have a (new) PMO issuing a Good Scheduler Practices instruction prohibiting the use of any form of explicit delay allowance or time buffer in our project schedules on the basis that it only extends the project duration and / or confuseres the crica...

Jan 11, 2011

Saving Baseline - Strange Issue

Forum Topic

Hi,   I am facing a strange problem in P6 Ver. 7; when I save my current project as a baseline and assign it as a baseline, then I see some variation in the dates of baseline with respect to the current schedule.   What could be the reason, please he...

Jan 12, 2011