Hi there,
I wonder if someone could remind me how I could sort this out?
I have 5 activities A, B, C, D & E starting at different times from now until April, I have them all linked into another activity (F)which I need to start with the earliest date of the preceeding activities. However the dates (A-E) start could change and I want activity (F) to reflect the earliest start of them all as and when. I've tried linking them via SS and FS and FF but none make (F) start date equal the earliest date of A-E.
Any ideas?
thanks all.
Thom
Hi Tom,
If I understand your question. Goto Task Type from activity form for activity F and make Type= Hammock while maintianing your SS relationship to each of A-E, and FF to each A-E.
But Note that F will have no effect on the schedule but will reflect what you want to see.
Regards
Bukola