Search

Simple P6 Question

Forum Topic

I'm sure this must be really simple to do in P6 but I can't work out how!I have a task that is % Complete Type Duration, Task Dependent, and Fixed Duration and UnitsIt is a task which has started and must end on the 17 September 2012I have set the Fi...

Feb 20, 2012

updating project

Forum Topic

hi everyone, i'm new to the field of scheduling.There are some things I want to ask about scheduling using ms pro 2007.- How to update schedule without resource- How to input actual start and finish.Thanks for the help

Feb 20, 2012

Group of activities

Forum Topic

Hello, Do somebody know how i can do group of activities to be able to copy this and save time when I am planning a new project? Thanks

Feb 20, 2012

Frequency of schedule updates.

Forum Topic

Hi, Please, correct me where I'm wrong. I remember reading on some SDPM paper that the schedule updates should be made daily to calculate the success probability trends ¿Did I actually read that or am I just  imagining it?Now, this "Daily update" is ...

Feb 20, 2012

CPA ASSIGNMENT HELP

Forum Topic

Hi, I have just started a basic construction qualification nd im starting to learn the basics of project scheduling. I have been given an assignment to create a Gantt chart, activity on arrow diagram and find the CPA aswell as noting the earliest and...

Feb 20, 2012

Manual Scheduling - Project 2010

Forum Topic

I have just received a copy of MS Project 2010 for evaluation. I cannot understand why it defaults to manual scheduling? The whole point of scheduling software is that it calculates the dates within a network? Why Microsoft see this as an enhancement...

Feb 20, 2012

Finish Milestone

Forum Topic

Hello All,I have Planned a Project and after Finalizing the Schedule I've just Noticed that the Finish milestone is Note Giving the Required Date.My Project will Be Handed Over On 15th Dec,2012 and I gave FF RElationship to Finish  milestone and last...

Oct 8, 2011

Project Exclusively Locked

Forum Topic

Hi Friends,,I have made a copy of the existing updated project to make the revision, I have revised this updated program , in doing so I have imported the resources data from the DBF file. I now want to make a copy of this program , but I am unabel t...

Oct 9, 2011

Changing Activity % Complete Back Zero and remove actuals

Forum Topic

Hi Everyone, I have encountered a problem in P6 update wherein I made a mistake for the previous week update. I want to change the percent complete of an activity back to zero and remove the actual date. The P6 wont allow me to change. Can somebody a...

Oct 9, 2011

Project Planning

Forum Topic

HOw many activity we can use in a single project and what's the no of relationshipe we can assign in same programme. means i have one programme in that 20000 nos activity with arround 60000 relationship i want to know max no of activity and relations...

Oct 10, 2011

Critical Path on Complete Project

Forum Topic

Hi Guys & Gals Quick question, does anyone know how i can find what the 'driving' activities are for a programme that is essentially complete? I have a programme that is marked up as complete (all activities are 100%) and i am trying to establish wha...

Oct 10, 2011

Primavera P6 Critical Analysis

Forum Topic

Hello I have a plan in P6 version 2 and after updating activity % and my Expense % Complete to match then schdulling it the end date for the enture project plan went from for example 12 october to 12 november. I don't know why this has slipped so muc...

Oct 10, 2011

SDK installation

Forum Topic

Dear All, I have P6 v.7 Inatalled SDK. My question is, How to start SDK Application? Regards to all Riad

Oct 10, 2011

Driving Predecessor Activity

Forum Topic

Hello All,I have seen a previous thread on this topic but i did't get Much idea from that.I just Want a Simple answer that If an Activity has More Than one predecessors then how can i Guess that which one of them is Driving the Successor activity. Be...

Oct 10, 2011

Urgent Issue

Forum Topic

ello All,our company install drainage pipe but another company working at same area during excavation break our pipe.......so what we do??Regards,

Oct 10, 2011