Hi Faiz

It depends on whether the other contractor is employed on the same project as you.

If yes then send a polite letter to your employer claiming delay and restitution for the dammege done by his other contractor.

If No then send a polite letter to the other contractor claiming delay and restitution directly.

Be sure to add clear photo's of the damage.

Best regards