Multiple imports of risks to Primavera P6

Forum Topic

Hi everyone,Is there solution ti import (through Excel) risks to large number of activities in P6 schedule?Similar to importing of activities and/or resources, I would like to define several different risks and then instead of using manual method in ...

Mar 13, 2023

Multiple import of risks to Primavera P6

Forum Topic

Hi everyone,Is there solution ti import (through Excel) risks to large number of activities in P6 schedule?Similar to importing of activities and/or resources, I would like to define several different risks and then instead of using manual method in ...

Mar 13, 2023

How to handle remaining quantities

Forum Topic

Vladimir, Rafael,How do you suggest to handle activities that are finished but they have remaining quatities?Explanations:I do not use earned value to track work. 99.99% contracts, either Design and Built, either Build will have bill of quantities wh...

Mar 13, 2023