Dejan Kezic 👤 Member for 8 years 2 months

Hi everyone,

Is there solution ti import (through Excel) risks to large number of activities in P6 schedule?

Similar to importing of activities and/or resources, I would like to define several different risks and then instead of using manual method in P6 to export file to Excel, then prepare it for importing by coping risks to different activities and return it through import.

I have tried it, but I can not find Risks in Available Options in Export dialogues.

 

Thank you in advance!

S
Santosh Bhat 👤 Member for 21 years 2 months

Dejan,

Interesting, Doesn't look like Oracle have made Risks available to be viewed in the export templates, or in columns or Grouping/Sort, even though they are linked to activities.

So there is no way to either populate the Risks or to assign them to activities.

Out of interest - what are you intending to use this functionality for, other than registering risks against activities, the Risk module of P6, doesn't do much.

Forum Sponsor

Top Posters

sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts