Importing activity codes in xer file

Forum Topic

HiThe first client xer programme that I import into a fresh standalone database will include the activity code assignments. However, when I import further updated xer files, the activity code assignments are not imported.Would be grateful if anyone i...

Jul 16, 2022

Spider Project Automation

Forum Topic

Vladimir, I am looking for a way to do update all material and resources costs on a weekly basis. Here is what I am thinking: 01. Use a database (doesn't matter wich one) as long as it can export a simple text file. The database will store codes of m...

Jul 19, 2022

The Planning Paradox - How much detail is too much?

Forum Topic

Traditional views tend to favour a management approach built on the assumption that more detail is better—and to a point, this is undoubtedly correct. Insufficient detail in a plan of any type is a sure way to fail.  But, there’s no right answer to t...

Jul 22, 2022

Deleting Multiple Projects in P6

Forum Topic

Hi,I have a requirement to datacleanse a P6 installation that has been badly maintained over a 10 year period.There are circa 4,500 projects (many with up to 50 baselines) that need to be deleted.The system is running on an old server and is extremel...

Aug 23, 2017

MS Project Alternatives on Mac

Forum Topic

Hi guys, New to the forum but wanted to get some opinions on what you use on Mac instead of Project? I know you can run it via a virtual machine but I'm not a fan of using Windows software on Mac this way. I've checked out some of these alternatives ...

Aug 24, 2017

Contract Modification to Descope - Delete Schedule Activities?

Forum Topic

Hi everyone - if your customer wants a contract modification to descope part of the project, do you keep the schedule activities for that scope remain in the schedule (with a modified activity name showing it's been deleted per the modification, 0 da...

Aug 25, 2017

Editing horizontal data in the graph

Forum Topic

Hello everyone, this is my first post and really appreciate those reply this thread. [[wysiwyg_imageupload:4981:]]For the graph, I want to edit the horizantal data. Meaning here want to change from 1 2 3 4 and so on to the scope,plan and others such ...

Aug 25, 2017

Forensic scheduling

Forum Topic

Hi, I have 15 years of project management experience and 12 years as a turnaround scheduler and scheduling manager on a large oil refinery. I am looking for new challenges and would like to try my hand at forensic scheduling (claims) Could anyone ple...

Aug 27, 2017

<deleted>

Forum Topic

Hi, I have 15 years of project management experience (General contacting, not oil and gas) and 12 years as a turnaround scheduler and scheduling manager on a large oil refinery. I am looking for new challenges and would like to try my hand at forensi...

Aug 27, 2017

Change Activity ID

Forum Topic

To add on activity after the baseline done is quite tedious process especially with activitity ID.Anyone can advise on how to change activity ID fastest way? Is it possible to use export & import function to excel?Thanks

Aug 28, 2017

Import file

Forum Topic

Hi Mike,I am trying to save file as XER to import it to P6 but got the attached error/warnings.http://imgur.com/a/E27khPlease advise me the steps to follow so I can save file as Full as it is without the above warnings and import the whole programme ...