Detaching the baseline

Forum Topic

Greetings to everyone. I have to detach the baseline to modify some duration and some calenders. After modification I am expected to re assign the same base line. Any Suggestion , what precaution should I take during this...? Thanks in Advance.

Dec 8, 2018

Client Instruction of Variation

Forum Topic

Dear All,We have 4 delay events in our project. First event has currently an impact of 124 days delay and is still not completed and it is the Client's reponsibililty of the delay. The other three events have been finalized and awarded 60 days EoT by...

Dec 8, 2018

Activity Gap

Forum Topic

Dear all,If for example I have one activity that has been commenced on the 4th of Dec, then the activity was paused on the 6th, afterwards it has been proceeded again on the 12th of Dec and totally finished on the 18th of Dec, how can I reflect that ...

Dec 8, 2018

MS Project- Progress Line

Forum Topic

HiI have an issue with the progress line in MS Project.I have a summary bar that has all the sub tasks beneath it with 0% complete. The summarry bar also shows 0% complete, but when the progress line is added to the Gnatt chart it shows all the sub t...

Dec 11, 2018

Progress - Summary Progress

Forum Topic

Is it possible to proclude the progress line from including summary lines? i.e showing an average of the progress of activities within this as this information isn't as important. I am more experienced in using Asta Powerproject, is it normal for the...

Dec 11, 2018

Resource Filter

Forum Topic

Hi all, Is anyone able to advise me on how createa a filter for a resource in the normal activities view please? The end result that I'd like is to be able to give each resource a pdf bar chart of their programme of works. I'm using Primavera P6 v17....

Dec 11, 2018

Restore P6 Pro Standalone (SQLite)

Forum Topic

Dear Members,I've P-6 file name as "PPMDBSQLite". This is only file as primavera database of all my projects. I want to access them on another PC. Could I access them? What should be the way to upload?I'm worried about this because this is only backu...

Dec 12, 2018

The general thumb rule of Fabrication Productivity

Forum Topic

Dear Sir, I am new in planning section . I am now preparing a planning sheet regarding fabrication work. kindly guide me how much productivity and manpower will consider in verious section fabrication.like 1. shop floor heavy fabrication .2 . on site...

Nov 19, 2017

Different duration for same Project.

Forum Topic

Hi everybody ,I am a new user of Primavera.I am facing an issue regarding total duration of a project which is showing two different duration in two systems. I have imported this project to the second system from the first One where it was created.I ...

Nov 20, 2017

Microsoft Project and Super Critical Bars

Forum Topic

Here's how to create Gantt chart bar in Microsoft Project to highlight activities that are already behind or super critical http://ed.gr/h3l3

Nov 20, 2017

change order and reflection in baseline

Forum Topic

All change order modify the baseline in some way, such as cost, scope or time. but we do not create a new baseline everytime.how do we reflect this change order which only modifies part of the basline, in the baseline?for example, lets say we are bui...

Nov 21, 2017

WBS Import from Excel

Forum Topic

I have created some development code that allows me to Import a WBS Structure from an Excel file into an XER File directly & have been testing this with my own projects, along with some made up examples to try & test it out properly.I am looking to f...

Nov 22, 2017