Delay Analysis in P6
Forum TopicGents,Can you please let me know, how easily i can define the dependencies in P6, in order to show the delay events. Cheers,Regards,Zaid
Gents,Can you please let me know, how easily i can define the dependencies in P6, in order to show the delay events. Cheers,Regards,Zaid
Hi All,How to identify the not started activity and slipping or negative variance activity compared to baseline using filter.
dear all,i created resource excavation budget is 22965 m3 at the beginning of the project & this budget by p6 divided as follows aug. 21872, at Oct. 608 & Nov. 216.which is not appropriate for the project so i need to adjust it manual per month on P6...
Hi all,It is 2040 and we're working on a major infrastructure project, what do we think project planning will look like? What will we do differently to today? How will we monitor progress?I would like to know your opinions on:what trends are emerging...
Hi guys Is anybody can guide me, my project start date & finish date is matching but the duration is not calculating properly , for eg. start date : 20-dec'16, finish date - 19-apr'18 , Duration should come - 474 days, BUT IT IS SHOWING ONLY 453 DAY...
I'm new user of primavera, so I wanna ask about importance of the activity ID ?
Hi everyone, Im loading weekly progress to primavera, then runing the program. But i meet a problem every week that, after loading the new progress values i see the past manhour values distiribution has been changed. I could not find a way to freeze ...
Dear,I need your help.I want to make mobilization plan for welding machine.Dia inches for welding is 201310.Can any body guide me.I am very thankful to you.e mail ([email protected]) Thanks
In Primavera P6 EPPM, it is possible to monitor your schedule deadline in relation to the current projected schedule completion date. Here's how http://ow.ly/ayy63072AIS
Hi Planners,Past three years am working as a project scheduler in primavera and my question is how to improve my ability to be a full-time planner.What are the things which I need to concentrate or work on it?
Hi AllFirstly. I am a lvl 3 planner. And a new one at that. More used to reviewing contractors programmes, than building ones...So. Question I am building a programme, where upon only we have a deliverable to be discussed at a weekley meetingProblem ...
Dear ExpertsProject Scenario - 80% Planned duration surpassed , contractor providing further structural design changes to Sub-contract(**MEP) with existing delay events from contractor i.e ( late civil clearance, civil rework impact and pending appro...
I have been asked to research into "examples of scheduling work" regarding "EPC" and "P6".Can anyone help me with any sort of information regarding thisIt is part of my development regarding my training into becoming a "P6 Planner".Kind Regards,Mike
Whch is the AISC Certified Steel Erection company in Ohio?
Here we look at what project start and detailed workweek mismatched times may have on your schedule’s total float, and start and finish times http://ow.ly/IFYW307g6lj
It is easy to output % complete from MS Project however I have not yet managed to find out how to output either: * Complete through - a value which appears to be only available to the Gantt graphic* The date circled in the picture below - i.e. where ...
Hello everyone,I am using P6 V15.2 and would like to clarify the fundamental difference beween start dates available in P6.1. Start2. Actual Start3.Anticipated Start4.Early Start5.Late Start6.External Early Start7.Planned Start8.Remaining Early Start...
Hi, I have recently started using P6 Standalone version to test it on 6-7 small scale projects. I haven't had the formal training yet and working on a local dbase. As an MSP user I got a few questions which I couldn't find the answers to in the foru...
Quick question as I don't have Primavera I can't answer a simple question: Can you copy and paste a simple table showing the items below out of Primavera and into Excel?Many thanks A reference (user entered number 1-200)NameStartFinishBasline StartB...
Hi,I have a detailed schedule which represents the works of 4 packages. Each package WBS has it own work packages and activities.I was trying to take the longest path of each package, by filtering each package and selecting also the longest path filt...