Im loading weekly progress to primavera, then runing the program. But i meet a problem every week that, after loading the new progress values i see the past manhour values distiribution has been changed. I could not find a way to freeze or luck the past on primavera.
could anyone can help me please.
regards,
Ilhami Sonmez
glad that I could help you
.
Sorry friend, i was trying to say thank you. There occured a problem.
by your help i solved my problem.
Thank you so much :)