how to add more items in code libraries

Forum Topic

HI,   I'm using Asta easyplan. I'm creating a tender programme. I'm trying to put all of the different stages into different colours so I used the code libraries option and dragged the headings to the tasks and then renamed the headings.. I assumed I...

Aug 10, 2011

Revised Schedule Problems

Forum Topic

To All Expert;I revised the baseline after 6 mos. of implementation because there are other areas to be added plus the variation order.The bottom line is after the said revision my s-curve start in the present data date, the previous %complete doesn'...

Aug 10, 2011

Query in Tracking

Forum Topic

 Hi Friends, Can any body please help me what is the difference between Update as scheduled & Rescheduled work in Tracking Wizard and where should i apply this ogic while tracking? 

Aug 11, 2011

Reference material for MSP

Forum Topic

Dear Friends, Can anybody please share the referenece material for MSP especially while tracking (Progress lines, Scheduling the work & Reschedule Work,etc..)   Please do the needful at earliest.

Aug 11, 2011

Convert from PowerProject

Forum Topic

Hi all Tilos users Is it possible to convert an Asta Powerproject pipeline programme in Task per Line mode directly into Tilos? Best regards Mike Testro

Aug 11, 2011

Imposed LAD to Contractor

Forum Topic

Are we entitle to charge LD to Contractor based on the following : - Natural of contract ( Infra structure work - 2.2km of main road , land scape , 2 bridges )- Contract completion 15 August- due to employer delay in the negotiation of the Electricit...

Aug 11, 2011

P6 - Additional 1 day duration

Forum Topic

In the programme I'm working using P6, I'm using "day" as the unit of time. I set Admin Preferences>Time periods to 24 Hours/Day. I did the same for the calendar. But for an activity with a 1 day duration, which will start on 08-Aug-11 00:00, it will...

Aug 11, 2011

Primavera Version 8.1 Installation?

Forum Topic

Dear Members I need some help in installation of Primavera 8.1 version. I tried the procedures to install earlier versions with various combinations of username and password, but no use. It is installting standalone New Oracle Express Edition databas...

Aug 11, 2011

NEC - EoT Entitlement

Forum Topic

Am I right in my thinking with the following.....   I have assessed a PMI and impacted the last Accpeted programme, as a result there is a 2 day impact to Planned Completion.   However when I then put these works in the current Draft Programme (with ...

Aug 11, 2011

Progress Measurement System for EPC project

Forum Topic

Appreciate your expert opinion on this... For an EPC project, we have a master schedule with 3 phases of work; engineering, procurement and construction. In our project, construction portion is using quantities as the basis for progress measurement, ...

Aug 11, 2011

COPY OF STEP BY STEP INSTRUCTURS

Forum Topic

Is there anyone out there who can send me the step by step instructions for P3 Planning.  I want an overview of the process before I start the course.   Cheers XXX

Aug 11, 2011

Difference in Orginal duration

Forum Topic

Dear  Friends .. I am facing a problem in  P7. I prepared base program and updated.while updating the program the orginal durations in different WBS Levels  are different .Is there any solution .Please help RegardsArun

Aug 11, 2011

Difference in Orginal duration

Forum Topic

Dear  Friends .. I am facing a problem in  P7. I prepared base program and updated.while updating the program the orginal durations in different WBS Levels  are different .Is there any solution .Please help RegardsArun

Aug 11, 2011

Primavera P3 error message #88

Forum Topic

Hello everyone. I am having a recurring problem with my P3. It keeps coming up with the error message "Problem opening project file ####REL.P3, reason #88"Has anyone had this problem before or does anyone know how to fix it? I've tried restarting my ...

Aug 11, 2011

Interview tips!?

Forum Topic

Hi, maybe I can ask tips from anyone interviewed by MUSANADA???? Thanks,

Aug 12, 2011

Project Structuring - WBS, Summary Bars, Expanded Tasks

Forum Topic

Asta Power Project Users, As the topic title, I was interested in what method of project structuring you use. I have always used summary bars to breakdown the project. Summary bars have always served me well for this purpose, using activity codes as ...

Aug 12, 2011

Quantities & remeasure

Forum Topic

We have a re-measure contract, while there is some ambiguity in the measurement rules we have demonstrated that our tender rate was based on the billed quantity. The billed quantity can be clearly demonstrated how it was achieved.Due to the ambiguity...

Aug 12, 2011

Physical Percent Complete Roll up

Forum Topic

Hi Friends, Is there any way around to have Physical Percent Complete Roll up at the top, the same way of Performance Percent Complete? Regards to All Riad

Aug 12, 2011

Problem with Total Float in P6

Forum Topic

Hi,I am currently working on a Infra Project were i wont be using the resources or levelling part,whereas i have to manage with the sheduling part i had already made the shedule now revising it again but have to maintain the total float as zero ,can ...

Aug 12, 2011

looking for a programme for Apartment block development

Forum Topic

hello guy & Dolls,I am Leo and am new here, i am a  project manager and now have set up my own small company, which is good but also it gives me some challenges, one being i am being asked to look at a development in Moscow Russia and it is for a 52 ...

Aug 13, 2011