The Barometer on Change: 5 Themes for Change
Forum TopicHi Guys,Moorhouse has recently released the results of their survey into what is driving change and how effective it is.Here's out take on it http://bit.ly/KNyhtFColin
Hi Guys,Moorhouse has recently released the results of their survey into what is driving change and how effective it is.Here's out take on it http://bit.ly/KNyhtFColin
Dear AllCurrently I am handling a project having a one month delay ,I want to prepare man power histogram , The histogram i prepared is based on Baseline and now it is not reflecting the exact situation of site due to delay1. Is it possible tp prep...
Dear AllCurrently I am handling a project having a one month delay ,I want to prepare man power histogram , The histogram i prepared is based on Baseline and now it is not reflecting the exact situation of site due to delay1. Is it possible tp prep...
Dear Planners,I am producing time scheduling for Pipe manufacturing, it is production line and the schedule is EPC (Eng. Procurement and Construction) the size of critical is massive as most of the activities are critical, is this right?Regards,Mouta...
Hi, Can Primavera (P6V7.0) level ident (parent/children) resource? Per example: Resource level 1: Unit maximum manhours; 50h/h Resource level 2: Electrician maximum manhours; 20h/h Resource level 2: Welder maximum manhours; 40h/h Resource level 2: pi...
Dear All, How can we generate a cumulative late curve from the resource usage spread sheet in P6. Your valuable remarks are highly acceptable.. Regards. Sunil.
Hi guys, How do I put a lag in a specific resource? Example is I have an activity with 10 day duration. A resource will be introduced half-way (after 5 days) up to completion of that activity. In P3 it was very simple. How about in P6? Thanks.
Hi;I have got separate schedule for Procurement,mobilization and construction from our sub-contractors.How to make these all as one project? Regards
Hi Guys, Check out our latest video tutorial on Primavera P6's resource leveling capabilities http://bit.ly/McQsZQ I hope you like it. Emily
Hi ,I have one question...In P6 , lets suppose i have multiple projects , Every project has its own organizational hierarchy (OBS)..... and for example i select one project and only want to take out the print of this projects hierarchy (not all) ... ...
Dear All, Why original duration changed when I import XER file and be not matching the start and finish date? I mean start and finish date show only five days but the original duration show 1 day. Thank you, HANSON
Hi All i am wondering if its possible to create progress dropline on Release: 6.2.1. Thanks
Hey everyone! Here is a link to our latest Primavera P6 video tutorial covering Claim Digger. It can be found in our website's Primavera software training blog or by following the link : http://mssprojectsanalytics.com/blog/bid/172152/Primavera-P6-Tr...
Dear all, please help me with the questions below, thank you. 1. When i status my schedule, i notice that sometimes when i check the status of an newly started work as "start", the duration in "at completion" row will change to a duration longer than...
I am just playing around with Linked fields in Ms project (Paste Special => Paste Link). This seems to be quite a powerful feature especially taking into account, that one can link both within file as well as even to outside file (e.g. even to Excel...
Hi All,I want to use claim digger but failed so far. When i open it and click the "select revised project" then at that moment only few projects appear in the dorp down list and i cannot see the full list. why is it so?. How to get the pop in of full...
Hi All,I want to use claim digger but failed so far. When i open it and click the "select revised project" then at that moment only few projects appear in the dorp down list and i cannot see the full list. why is it so?. How to get the pop in of full...
Hi Forum, I have opened up two projects together in P6 and have been copying WBS elements in the WBS window from one project and pasting them into the other. This pasted WBS levels and activities into the second project. All the sudden when I copy ...
Dear all I prepared a man power histogram from actual dates ( actual start and expected date to finish ). there are activities alredy started and compleated 50% and consumed 50 % of man power, but the generated man power histogram not showing any r...
After I press F9 to re-schedule a box appears on the screen, asking what date to straighten the progress line to. I turned that box off, and now I want to turn it on again. How do I do this ?? Thanks Ronan