Cash Flow in P6
Forum TopicHi all planners I am quite new in planning. In P3 it was not difficult for me to get the cash flow, please don’t make a joke of me, but in P6 I am not able to get cash flow even after a year working on P6. Tanveer
Hi all planners I am quite new in planning. In P3 it was not difficult for me to get the cash flow, please don’t make a joke of me, but in P6 I am not able to get cash flow even after a year working on P6. Tanveer
Hi all planners I am quite new in planning. In P3 it was not difficult for me to get the cash flow, please don’t make a joke of me, but in P6 I am not able to get cash flow even after a year working on P6. Tanveer
Dear All, In Admin Preferences , Earned value tab , we have 3 methods to choose earned value 1) Budget value with Planned dates. 2) Budget values with Current dates. 3) At completion value with current dates. I have a clear idea the use of the first ...
Planners I am trying to carry out a hook time analysis on a insitu concrete frame. We are trying to establish which subcontractor is more realistic, one is saying 3 cranes the other four. Has anyone got a worked example of a similar exercise? Many ...
hi all, you know, in the resource assignment view, when you change a resource for another ?P6 asks if you want to reset the remaining units/time (or something like that) for the new resource ? a colleague of mine accidentally checked the box hiding t...
Hi, Can anyone tell me why that when i assign the P6 web portfolios license to a user, they cannot see a programme Gantt Chart when they click on a Project in a my projects Dashboard on the web.
Hi, Can anyone tell me why that when i create a report to show in Timesheet Approval Reports via the Web Client. That you cannot show all the borders and have one record per page as per you would if you were viewing or Printing in the Project managme...
Hi all planners, I am quite new in planning. In P3 it was not difficult for me to get the cash flow, please don’t make a joke of me, but in P6 I am not able to get cash flow even after a year working on P6. Please give some hints or advice. Tanveer
good evening to all please can any one advice me, where can i find a good center in Jordan to study contracts & claims best regards jihad aldoaud
Hi, Please refer me to some web page or book for report making and cost accounts or describe it in here if possible. What I am doing is to create a resource “C” and assign it the value of my B.O.Q. but I got the idea from your above said reply is to ...
Anybody can help? I'm not able to see in the same window (as with P3 and P6v7 Client) barchart and resources. best regards
Hi all, We are working on the same programme in three different system in different Area. (example the programme has Area 1, Area 2 & area 3). I want to know how to import the assigned relationship from other two system.. Due to time constranit we ar...
Hi all, We are working on the same programme in three different system in different Area. (example the programme has Area 1, Area 2 & area 3). I want to know how to import the assigned relationship from other two system.. Due to time constranit we ar...
All; I've been asked to graph the percent complete of a project in P6. The project has a total duration that it must meet. The simple, linear way, would be to just graph the schedule percent complete on the linear total duratino and call it a day. We...
All; I've been asked to graph the percent complete of a project in P6. The project has a total duration that it must meet. The simple, linear way, would be to just graph the schedule percent complete on the linear total duratino and call it a day. We...
Hello Fellow Planners, Has anyone ever produced a detailed crane lift program? Anyone experienced a contractor who submits one? Any examples of the above would be appreciated. Thanks in anticipation, Craig Adams
Hi all, I have some issues, I need to use Expense Cost and Man-hour related progress. I want to see the Planned progress and Actual progress based on the Expense Cost and Man-hour same time. I believe we can load Expense Cost as well as Man-hours to ...
Hi all,Have been doing a lot of resourcing work & filtering a lot in the resource assignment tab. When i filter by my codes in the resource assignment I cant seem to save the filter like you normally can..... Any suggestions so I am not doubling up o...
Dear Planners, the resource in the directory bar, all the resources are displayed and to include the resources of the project by using filter (in the left corner) the program ask you to delete all the displayed resources. How to include the resources...
Hai If anyone of you Have P6.7 Web access Manual & installation Procedure plz mail to my mail id [email protected] Regards Anbin