change a resource assignment

J
Johnny Pain 👤 Member for 20 years 8 months

hi all,

 

you know, in the resource assignment view, when you change a resource for another ?

P6 asks if you want to reset the remaining units/time (or something like that) for the new resource ?

 

a colleague of mine accidentally checked the box hiding this question for the future AND the wrong answer, so each time he changes a resource for another, it resets the upt with the default value set for the new resource.

 

where can we find the option in P6 to put it backwards ?

or can we make P6 ask again for each change ?

 

I tried different settings in the project/resources and project/calcultations tabs but I can't find it...

 

thank you !

 

 

djo

F
Ferdinand U. 👤 Member for 18 years 11 months

edit menu, user preferences, under calculations tab, Assignment Staffing, check the option "ask me to select each time i assign"

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts