Forum TopicDear Planners, I have two WBS, let's say w1 & w2, the activity ID default is A and incremental by 10, it means A10, A20 and so on. How to change activity ID for w2 to become B10, B20 and so on instead of A. Regards, Moutaz
Dear Planners, I have two WBS, let's say w1 & w2, the activity ID default is A and incremental by 10, it means A10, A20 and so on. How to change activity ID for w2 to become B10, B20 and so on instead of A. Regards, Moutaz
Does P3 support project version history tracking? For example I would like to view an audit trail of project changes and potentially roll back changes if needed. Thank you,
Hi planners, Can I have your expert Advice? The Sequence of Activity thru my program, approved by the consultant was not followed on site. Being a Planner how should i react? Thanks, Nanding
Could anyone explain how to get P6 to report the float levels correctly after resource leveling?An example...I have two 20d activities of pipe laying, both starting on the same date but both required for commissioning. The current float is reported a...
Hi all,Is it possible to import a project with its baseline to P6?Thanks in advance,Utku
I am looking for someone to work remotely doing P6 development using the API and SQL. I am looking to import P6 data from customer file. Build a customized bridge to automatically import specific p6 data from the customer file to Create dashboard, fo...
Ok We are using p6 and on a task that has not started the original duration is 90 units and remaining duration is 90 units. I need to change the Original duation to 50 units as the crew has found a method to do the task quicker. When I change the o...
This web site is a directory of open source project management tools for planning, estimating and tracking software development projects http://www.opensourceprojectmanagement.org/
Has anyone come across to this problem in P6: when I import a MSP file to P6, cause This error:"Cannot save projectMicrosoft Project does not support saving projects into ODBC, MPD or MDB formats. Please save the file in a format that is supported by...
Hello everyone I am cost loading my programme,we use sub contractors for majority of our packages.there is a lumpsum amount for the subcontract packages. do i assign it propotionally to all the activities ?or is there anot...
Hi There is a project and its member projects. The activity IDs of one member project was manualy changed (exclusive access etc etc)... So when I open "mother" project - all its member projects open... but when I try to open member projects indivi...
Hai One of my Colleague is facing problem with following Issue i 1.Cannot delete the project beacuase the project is in Share Mode How can we Change the project from Share Mode to Exclusive Mode . He using P6.7 Oracle Database 2.When he Check the Use...
Hi I want to create the project control room. here i want to know that what is sequence of activity.For example 1. Concept Note by Electrical department 2. assignment drawing to Civil & Structure, HVAC, Instrument 3. HVAC gives the assignment to CI...
How to update in M.S with proper way when i update some activities take dates befoe data dates
Hai In Project Detail option i Set Default Calender - >7 Days Work Week & Enterprise Calender -> 7 Days Work Week But Still The Summary Bar is Taking Activity Calender(Standard 6 Days Work Week) In Calender Option-> Used By Also it is Not Showing P...
When I am doing the activity ids renumbering in P6v7, error mesage is showing and the renumbering is not working. I have attached the error message below: [[wysiwyg_imageupload:351:]][[wysiwyg_imageupload:352:]]
Hello, I am working on the development of a master plan for a program to control flash floods in a mayor city, and I am looking for reference(s) to similar project(s) in order to validate durations. The project is located on a coastal city inhabited ...
Dear all,I need a help to find the scope of of work for civil work in construction phase in underground railway project.the project is located in a modern and busy city.Which methodology that I have to use cut and cover method or tunneling?I wish you...
For all planners are keep asking about S-Curve the Artical has been written By: David Garland Introduction The first time most project managers become aware of the existence of S-curves is when they are requested by the client or senior management to...
Hi everybody, I'm currently looking to start a project planning career and have enrolled on to a 2 day course Introduction to Microsoft Project so I can get the ball rolling, has anybody got some advice on what other courses I can do or good places t...