Ressource assignement
Forum Topicdear all ,Please i want to remove a ressource assignement from tasks by global change (to be quiquely) wich formula suitable.thanks
dear all ,Please i want to remove a ressource assignement from tasks by global change (to be quiquely) wich formula suitable.thanks
I am trying to link 2 simple activities together on a straight "FS" relationship, the problem I am getting is that the following error comes up. I have tried copying the program, Export / Import, and even delete / re-create the activities (which are ...
Dear everybody.When I delete the project in P6, event window pop up. An application event has been intercepted. Please note the event code for reference.Event code DELET-1606-3 Then, somehow I can't delete this project and even one activity in this p...
Hello Everyone,Just a topic to know what will help Claim Management in a Project from which we (Contractor or Subcontractor) can calculate the delay charge.In most of the Contract Client would have already mentioned the amount which will be charged p...
getting the following error vent : Error LIOOB-1084-4 only for one user cant replicate.thanks[[wysiwyg_imageupload:2869:]][[wysiwyg_imageupload:2870:]]
Hi all,I'm looking to produce s-curves using Primavera, so far it's ok.But then, when I display the cumulative curves for budgeted, actual and remaining activities, the bugeted one shows as it should, the remaining one shows as well, but the actual u...
Hello,I do have a problem migrating from P3 to P6. Everything seems fine except that the total float on the migrated schedule on P6 is 1 day less than the total float on the the original schedule on P3.Did anyone have such problem before?! Can anyone...
Hello and good day everyone! I am a new membr to the site. I have decided to learn the P6 version of Primavera, since most of my colleagues in the industry use this, and i desire to be more proficient. I am a Construction Manager, working in the inte...
HelloI have an assignment at my University in which I should write about Data Extraction in BIM. Does any of you have some interesting readings related to this topic? Ways and means of data extraction, for which purposes and how it is used... As far ...
I am trying either import an MS Visio File into MS Project or export an MS Visio File into MS Project. The instructions are pretty straight forward in Visio for exporting a file from Visio and the instructions read as follows: On the Timeline tab, c...
I am trying either import an MS Visio File into MS Project or export an MS Visio File into MS Project. The instructions are pretty straight forward in Visio for exporting a file from Visio and the instructions read as follows: On the Timeline tab, c...
I am trying either import an MS Visio File into MS Project or export an MS Visio File into MS Project. The instructions are pretty straight forward in Visio for exporting a file from Visio and the instructions read as follows: On the Timeline tab, c...
Hi,I'm managing several project schedules all of which have the milestone task GoLive. I want to be able to capture the date into a custom date column I've created. Is there a way to do this via a formula or other method?Many thanks for your help.
Hi,I'm managing several project schedules all of which have the milestone task GoLive. I want to be able to capture the date into a custom date column I've created. Is there a way to do this via a formula or other method?Many thanks for your help.
In the project which I am working on, most of the activities have more than one predecessor/successor links(usually 5+). Also, no. of activities is 1000+. If I link all of them, the time-distance view looks much clumsy and there is no clarity of sche...
Hi All, Contractor agreed to submit acceleration schedule.What I understand about the acceleration is if the project delay is 8 months, and if Contractor agreed to accelerate in 4 months, they need to compress the schedule from 8 months to 4 months.I...
I am trying to build and level a resource loaded schedule. A number of the activities require part-time effort, that is to say just a few hours a day over an extended period of time. Unfortunately when I level these activities in P6, it refuses to a...
Hi all,I have a building project in prima vera Orcale R8.1. I have resources of labour,Mason,Steel fixer.I know their average consumption per hour like for example,labour takes 3cft/hr for excavation.My problem is that how do implement this data in m...
Hi, I work on a number of projects that are so big I need to apply filters to them to print out obviously so I don't have to print the entire plan every time. My Problem is, when I apply a filter to the plan e.g. remove task that are 100%, the baseli...
Can anyone email me an xer of the sample files for E&C, P6 v7? I'm having problems installing from the jar files. TIA-Carey