Calendar for scheduling Relationships Lag

Forum Topic

Hi,I have the following issue regarding how Primavera calculates lag between activities depending on the "Calendar for scheduling Relationships Lag": I have inherited a programme that has been set to calculate lag with the 24 Hours Calendar. That pro...

Jan 3, 2017

Aegis Project Controls Officially Launch Rubix 5.5 in 2017!

Forum Topic

What is Rubix?Rubix is an analytical tool that improves project controls professionals’ scheduling efficiency and accuracy. What scheduling software does Rubix work with? Rubix works with Primavera P6™. (You can connect directly to a P6™ database or ...

Jan 4, 2017

Matching the resource loaded MSP Schedule with Resource loaded P6

Forum Topic

Hi friends, My MSP Schedule is matched with P6 schedule in terms of duration, Pre & Suc, leads & Lags, resources, calendar. Without leveling the resource, the both MSP and P6 is matched 100%. When enabling the level resource option in Both, P6 dates ...

Jan 5, 2017

Visualizer Help

Forum Topic

Hello,I have been using Primavera for a while, but never used the visualizer before. I wanted to give it a try.  Either I start inside from P6 or from Windows. Available projects list is always empty. Do you know any specific reason or any solution f...

Jan 5, 2017

Defining Job Site Headcount

Forum Topic

Any suggestions out there on a way to extract the amount of actual bodies I will have on a jobsite after I have all my resource loaded.I suppose I could export the units out to an excel spreadsheet and get it from there based on my units max per day,...

Jan 5, 2017

User defined field name changed

Forum Topic

I'm working for a chemical company in Germany with different site locations. We all use Primavera P6 to plan our turnarounds.A strange thing happened yesterday. Suddenly we noticed after logging in that a user defined field which we have created at t...

Jan 6, 2017

Crew Size and composition

Forum Topic

             First of all, thanks to all the contributors who have provided their invaulable ideas and experience. My one main concern while deleoping the schedule is the resource loadng. The one piece of information I am falling short is the crew si...

Jan 7, 2017

Time distributed costs to Excel

Forum Topic

HiI want to export time distributed costs to Excel to include resource and expenses (which are loaded to milestones). There are reports in P6 that will do the resource costs but not the expenses. I want to the costs to be time distributed by financia...

Jan 9, 2017

Total Manpower

Forum Topic

Dear All,, I got a project that will complete within 2-1/2 yrs with estimted manhour of 175,000 Hours, I drafted a schedule that loaded with manpower. Expert advise how much direct workers required to complete the work activity. Thanks a lot.RegardsR...

Jan 9, 2017

Resource Id's not importing from SubContractor Schedule

Forum Topic

Hi,I am importing an updated schedule into our EPS and since the last update, I am not getting any Resource Id's. Budgeted Hours are fine, just no res. id's.Always importing as a new project, and previously did not have this issue. Contractor has pro...

Jan 12, 2017

Suggest tablet to use Primavera P6 Professional

Forum Topic

Hi All,I'm planning to buy a new tablet, as i travel alot, i want to buy a tablet which can access p6 professional compactably.Kindly suggest performing tablet for P6 on budget.

Jan 13, 2017

Adding to activity duration vs Lag

Forum Topic

What is the correct or preferred way to do this and why. Say you have a concrete activity that will require 4 days to complete and then 7 days to cure out before you can erect steel. Do you create an 11 day activity (4 days + 7 days) with relationshi...

Jan 13, 2017

Creating a non splitable task

Forum Topic

I have a situation where I have a task of 25 days duration that cannot be split and a shutdown period of one month. What I'd like to be able to setup within Project 2013 is the 25 day task so that it ends no later than the start of the shutdown perio...

Jan 16, 2017

Recovery Schedule

Forum Topic

I was requested from the consultant to make a recovery schedule on my latest updated , it show delay 42 days on the end of the project .what should I do ?

Jan 16, 2017