Search

Default Curve To All Resources

Forum Topic

Can we assign / change the default curve on all the resources that are assigned on activities?Like i want to assign a TRAPEZOIDAL curve to all the resources on all the activities.

Sep 17, 2010

Define fields in P6.

Forum Topic

Hi Guys, Trust you are doing good. I am trying to define a field in P6 and make P6 calculate its value in the future like we can in excel. I know how to define a user field and classify it as a number/start date/integer etc., but is it possible to pu...

Sep 17, 2010

schedule percentage complete

Forum Topic

how can i create a graph of schedule percentage complete, schedule plan & actual together. I have not added any resources yet nor costs in the project. but say, I have information that out of 100 activities 40 activities have started and out of this ...

Sep 17, 2010

Microsoft Project

Forum Topic

Hi guys!can anybody help me where can i download a microsoft project software? i tried some torrent sites but i always got the microsoft office software..any torrent/link/website please? thanks a lot..

Sep 18, 2010

Level-3 Schedule

Forum Topic

Hi -Experts, We got (awarded) one project that is Chemical Plant Project size is small .project duration is 13 Months, Project manager asking me to prepare a L3 schedule while i do not have enough information to do so, information like Procurement , ...

Sep 19, 2010

Other Program Change upon Global change

Forum Topic

 Dear experts. What is the possible mistake done upon having a global change  with a program "C" that other program "A" and "B" in other EPS changed also as what in program "C"?. Global change is Rebaseline. Program "C" is a copy of program "B" but d...

Sep 19, 2010

Productivity Reference in P6

Forum Topic

I hope I am not putting myself in trouble. I have transferred a productivity book to P6. It's from the KSA Chamber of Commerce dated 2007. I wanna share it but I am thinking I might be putting myself into trouble. It's almost 98% done but I don't hav...

Sep 19, 2010

P6 Export of estimated weight and user cost in WBS level

Forum Topic

Dear all,In WBS page we have the Estimated Weight and User Cost for each WBS i try to change these values using any tools but i failed also try to export them in excel but also failed.i try to add different weights like Cost weight, Equipment weight,...

Sep 20, 2010

How to keep activity dates after levelling resource

Forum Topic

Hi everyoneI have a problem with preserving dates after leveling. For example i have totally seven activity; six of them linked FS  and other one is not have any successor or predecessor. Thats why two activity start with project start. After applyin...

Sep 20, 2010

Lost resources & Cost during export/import

Forum Topic

Hello Guy! I have problem regarding my schedule loaded with resources & cost, everytime I export and import the project I lost the budgeted cost that I have loaded in each activity.. Any solution to my problem...

Sep 20, 2010

Construction in Tanzania

Forum Topic

Hi Everyone, I want to get a brief idea about typical working hours, methodology and plant used in construction in Tanzania. Thanks in advance. Re, Kin

Sep 21, 2010

Primavera 6.1 Log in Problem

Forum Topic

A bit of a strange one this, we are using P6 on a server, I can log in as myself without any problems, but when I try to log in as admin I get an error message and get booted off, but strangely others can log in as admin on different computers withou...

Sep 21, 2010

Building of paper combine

Forum Topic

Misters, good afternoon! Share practical experience of planning of building of paper combine. Thankful in advance

Sep 21, 2010

Resequencing programme

Forum Topic

Hi everyoneHow do i resequence a programme half way through the project.can i freez all the progress  and move the bars to a future date.what is the best practice.i work with asta power project.Thanks

Sep 21, 2010

Export Activities and Resource quantities

Forum Topic

Hi...my request is the follow... I need to export the activities and the resources for each one of them...but with the quantities of each resource asigned...i put the column resources but only appear the name..no the quantity...so...how i can export ...

Sep 21, 2010

Start Milestone FS Task Dependent Activity (Date problem)

Forum Topic

HELP! Well I thought this problem was taken care of in P6.7, but so far I’m not seeing it.  I have a START MILESTONE tied to an activity by way of (FS).  My milestone start on 9/15 and its successor should on 9/16, but instead it start on the same da...

Sep 21, 2010

Escalator Installation

Wiki Page

Modular Design Escalators PackagesThe escalator trusses are usually delivered in 1.6 m cubes, which include the internal workings etc. Normally 3 to 4 sections go to make up a standard escalator (an 11 m rise), however sizes and lengths vary greatly....

Feb 7, 2009

Road Markings

Wiki Page

Road and Car Park Markings 75 mm road lines = 20.5 m/hr Road writing = 3.5 hrs/word or symbol

Feb 8, 2009

Road Surfaces

Wiki Page

Barber Greene 8798 machine laying 100 mm in two coats (m2/hr)... Tarmacadam = 160.0 Asphalt = 145.0 Manual laying 100 mm in two coats (m2/hr)... Tarmacadam = 7.7 Asphalt = 5.0 Average laying of Asphalt wearing Course=40 Ton/hr so one crew can do 400 ...

Feb 8, 2009

Covered Steel Footbridge

Wiki Page

Simple universal beam steel bridge in modular sections, welded on site. 16 truss sections each 15 m in length, supported on H-frame vertical columns / supports.Support Steelwork Fabrication (4 bays) = 25 daysSupport Steelwork Erection (4 bays) = 30 d...

Feb 8, 2009