Cannot get Tertiary Baseline start & finish date columns to show up

Forum Topic

Have a project where we had some issues and had to create a "Recovery" baseline.  We had set a project baseline at the beginning and had been showing the "BL Project" start and finish date columns and when I set the recovery (tertiary) baseline, went...

Nov 17, 2011

What dose "As-Built" mean?

Forum Topic

Dear All Planners,What dose "As-Built" in engineering terms mean? and what is the diffrent between "As-Built" and "as recorded" which one is best to use?Thak you,Hanson

Mar 29, 2013

What is a 3D structured schedule?

Forum Topic

it's simply a classical Gantt wit explicit task name, and strong codification on the three axis of the 3D WBS:http://3d-wbs.blogspot.fr/2013/03/part-77-what-is-3d-structured-schedule.htmlBR, Jean-Yves Moine

Mar 30, 2013

Task Duration in Ms Project 2013

Forum Topic

Hi All,         When adding a Task duration should we also include the no. of weekends also. Regards,Mahzaj 

Mar 30, 2013

Activities & bars does'nt show

Forum Topic

Dear All, Suddenly my P3 files does'nt show the activities and bars. Even if you filter "All activities" it appears empty, but by viewing PERT all activities are there. Can somebody help me where can I find the setting of this one. Thanks, Angel  

Apr 2, 2013

Import data to Tables

Forum Topic

Hello is it possible to import data to tasks, resource, calendars Tables ? mimoune

Apr 4, 2013

Risk Management toools: suggestions to purchase

Forum Topic

Dear planners,the company in which I am working got a job where a risk management tool is required. I am a "skilled" planner using Primavera P6 but I never used a risk management tool. My company asked me to buy a new software to better plan/control/...

Apr 4, 2013

Adding Milestone Total Column to Enterprise view

Forum Topic

Hi,Does anyone know if it is possible to add a column to the customised view of the "Enterprise" to show total milestones in the various plans similar to how you can have the column showing "total activities" ?Thanks in advanceBob

Apr 4, 2013

Define a generic resource with a budget manhours

Forum Topic

Hiis it possible to define ageneric resource let's say Direct_Labor, and assign a budget hours for different activities.it seems spider calculate the budget hours based on the duration, calendar, can i orerwrite those values. regardsmimoune

Apr 5, 2013

Japanese Blog on critical path drag draws major interest

Forum Topic

I notice that there seem to be quite a few PP members who list a professional relationship with Japan Gas Co. Dr. Tomoichi Sato, who teaches at Tokyo University and does risk analysis research for Japan Gas Co. sent me the following email a few days ...

Apr 5, 2013

Time Impact Analysis (TIA)

Forum Topic

Alsalmu Alikom,Hello everyone .. I like to greet you all first ... I have an important question and I hope that you take advantage sensitive if possible ... I work in infrastructure project ... In short ... the beginning of the our project was the fi...

Apr 6, 2013

Comparison to the baseline

Forum Topic

a Very simple question how Spider make reference to the baseline activities, does it use the activity code ( activity ID) ? or the internal identifier ( i hope it is not the identifier) ? regardsmimoune

Apr 6, 2013