How/Where to Learn P6 and become a Planner
Forum TopicI am looking at a career change and would like some advice. Thank you
I am looking at a career change and would like some advice. Thank you
Hello Everyone,Just a topic on Change Order but Internal. Say a situation like, "Its a Engineering Project. The Client has given the Scope of Work and the Contractor has prepared a deliverable list. But at one time Contractor came to know that this d...
Here's a quick tip to apply actuals to a schedule when everything goes according to plan http://ed.gr/d81e
Dear All Master Primavera<I am Prastya, I am is newbie to used primavera P6 in my project and still to learn and explore for this software,I have problem during making the schedule, because in my project now already start work but the owner not stat...
P6 Professional 16.1 will not add new pred or succ in Window but will using highlight and button combo. It is almost as if something is keeping the add activity window from popping up. I will pop up if I click an existing predecessor and change it ...
Hi all, I want the know how to update my P6 schedule based on activities original duration- project actual % complete. so i can compare it later to the Master baseline, i've tried project (Duration % Complete). but it doesnt seem to be accurate.Note...
Is it possible in MSP for activity durations to extend when the project runs late?I'm trying to show the Project Management activity extending when the project is delayed, and showing an increase of hours required. I've tried using a Finish - Finish ...
How to Safe & Fast Remove Asbestos Roof Sheeting in Sydney?
Hello all, I am considering going to Uni next year and I would like to know which course would help with me further my knowledge of Primavera as I am at a begginers level currently. Also what is the best free online course/info for learning the fu...
Hi All,I'm just wondering what are the key components for a good project plan / schedule?I'm thinking the basics 1st, e.g. Start Milestone, Key Deliverables, good WBS, Resources, etc.Any thoughts? What would you PMO say it's right?Thanks!Sunchana
Hi everyone,Can you sharing or providing me and somebody else your experience/information about Refinery/Plant Turnaround/Outage using Premavera P6? I have experience my first turnaround scheduling using P6 but I think I have so many thinks to work ...
Hi everyone, can you please help me on my problem regarding prdeccessor finish date and successor date is same? Take note iam using more than 3 calendar work days. I appreciate your immediate response.
check out this new website http://engineerbook.net EngineerBook is a free professional networking and community for Engineers only all over the world, where Engineers can connect, share information, get knowledge, search for jobs, ask questions, shar...
Hello all,Anyone has used Primavera Unifier to manage shutdowns and turnarounds. I.e. preparing job packages, monitoring planning activites, costs, etc.I'd also to know if you recommend any excellent solutions to do so.Thanks.
Hi,Currently I'm working on a Master Work Program using the Resources Dictionary where all the completion are based on the quantity used. However, when I do the Earned Value Cost (EVC) report, I noticed the EVC is zero due to the Performance % Comple...
Here's how to level resources within activity total float in Primavera P6 Professional http://ed.gr/ekv0
Hi, how could i solve my problem on how to correct my earned value cost calculation on my updated Schedule in P6. Example of incorrect earned value cost is 2500USD instead of 6500USD at 100% Physical % Completed. Is there any way to resolve this issu...
Dear, I have a project with 6 phases each has different contractual completion dates and liquidated damages. But all phases are inter-related. I consider they should have their own critical path.It means the programme should have 6 critical paths. Wh...
Hi,I am analysing a program for a dispute. The dispute occured part way through the project so the delays are retrospective but the impact is prospective.My client, I beleive by accident changed a calendar for a future few activities from a 24x7 to a...
Hi all,in order to define scope of the project, we need to define the requirements and it might be all the requirements are in the sope or we might identify some of the requirements to be included in the scope. Two questions i have:1- what is the bes...