How to relate Material Cost to Earned Value Cost

Hi,

Currently I'm working on a Master Work Program using the Resources Dictionary where all the completion are based on the quantity used. However, when I do the Earned Value Cost (EVC) report, I noticed the EVC is zero due to the Performance % Complete is not inserted with any value. The problem here is, when I insert the Performance % Complete to 100%, the EVC become higher higher than my Actual Material Cost. I put the activitiy completion type as Unit Type, but I cannot key in any value to the Performance % Complete. When I change to Physical Type of completion, the Performance % Complete become 100% and the EVC suddenly jump up exceeding the Actual Material Cost.

Hopefully someone can suggest how to overcome this matter.

Thanks in advance.

Regards,

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts