Search

Earned Value - Man Hours

Forum Topic

Hello Everyone Can EArned Value be caluclated for Manhours and Then can we forecast the expected manhours to complete. I made a table to put those thing to get a forecasted manhours which is based on Productivity which is same as CPI. Please comment ...

Feb 16, 2017

New to planning - advice for my first few weeks :-)

Forum Topic

After doing somewhat of a 'covering role' - At last i have started my Project Planning career! And I am after some advice for my first few weeks. Just a couple of items on a list I can tick off, to benefit me - and of course. Should I end up working ...

Feb 16, 2017

Highrise construction diagram

Forum Topic

A new chart in the projects - Diagram building construction.Does anyone know how to work with this new diagram ?thanks. 

Feb 16, 2017

SF link pulls successor into non-working period

Forum Topic

Hello All,I have had this issue on multiple projects and was wondering if this was a flaw in P6.Whenever I apply the SF link, the link pulls the successor into non-working period. Here is how the 3 activties are linked.Activity A  <----  Milestone B ...

Feb 16, 2017

Estimate to Complete (ETC) Calculation

Forum Topic

Hi,Estimate to Complete (ETC) values are not changing when I'm changing its calculation criteria under the WBS Earned Value settings. Following are the settings of my programme in P61) Duration type: Fixed duration and units2) Percent complete type: ...

Feb 17, 2017

Remaining Units on Manual Resource Curve

Forum Topic

Activity 4 weeks in duration, duration % complete, 100 Planned Units added as resource manual curve over the 4 weeks as 50 20 20 10. Activity started on Baseline Start date, Exoected Finish applied as per Baseline Finish. Data date moved on a week. P...

Feb 17, 2017

Performance Percentage Completion ?

Forum Topic

Hi, Performance percentage completion: On updating the P6 Program of works monthly (Jan 2017 to Feb 2017)overall percentage completion (Performance Pct Complete ) found to be decreased ,is there any reason behind it?Regards,Jossef

Feb 18, 2017

Productivitu analysis

Forum Topic

Hello... Dear experts, Can you please help me for productivity analysis of construction manpower. Anybody has excel sheet will really help.

Feb 18, 2017

Time Impact Analysis in Complex and Mega-Scale Project Programmes

Forum Topic

Hi All,In a detailed contractual programme where we have around 40,000 No. of activities with proper weekly updates and around 600 Engineer's Instructions / Site Instructions; If the programme logic is not altered after a point and it is not reflecti...

Feb 19, 2017

Assign Budgeted Cost Automatically

Forum Topic

HI,I have activities with resources, each Labour resource has its own Price/Unit, Max Units /Time is 100%, I have set Duration Type to Fixed Unit per Time because if I have to change the duration of the Activity I want to change as well the budgeted ...

Feb 21, 2017

Setting Up a Four-Day Work Week in Microsoft Project 2013

Forum Topic

We've recently had a few questions on how to set up a four day work week in Microsoft Project. So here are step-by-step instructions, complete with screen shots, on how to do this in Microsoft Project 2013 http://ow.ly/Di1uX

Oct 24, 2014

Global Change or filter based on Min and Max dates

Forum Topic

Hi Guys,Hopefully there is a genius out there that is an expert with filters and or global changes, I am after a solution and can’t work out if it is possible to do in P6. Based on a filter (using codes to select a group of activities) I want to writ...

Oct 25, 2014

Pluses and Minuses for upgrading from 7.0 sp4 to 8.?

Forum Topic

I've been happy with what I can do in P6 stand-alone version 7 professional.... What am I missing?  Can I upgrade and stay stand-alone?Why should I abandon what I've got now?I'm just trying to get a user's view of where I go next.... or don't go next...

Oct 25, 2014

SChedule Behavior

Forum Topic

In my (construction) programme (P6 v7) three Level of Effort activities in the second level of WBS are linked with the first activity “Commencement of the Project” with “SS” relationship and the last activity of the project “Project Completion Date” ...

Oct 26, 2014

Report Wizard

Forum Topic

Hi thereSome report wizard are protected against modifications.Is there  a way to open it in aim to customize it , I have already export it and an rename it ,  but  when I  import it again it is still not possible to open it.RegardsKamel

Oct 27, 2014