Performance Percentage Completion ?

Hi, 

Performance percentage completion: On updating the P6 Program of works monthly (Jan 2017 to Feb 2017)overall percentage completion (Performance Pct Complete ) found to be decreased ,is there any reason behind it?

Regards,

Jossef

M
mostafa yousef 👤 Member for 9 years 3 months

Thanks alot Kannan. As you said there was increment in the budget. 

 

Problem is now resolved. 

 

Thanks

K
Kannan CP 👤 Member for 18 years

Hi Mostafa,

Make sure that your Total Budgeted Cost is not increased. Also check if the previous month progress for any of the activities is reduced, as a correction.

Best Regards

Kannan