Search

Multiple Critical Paths

Forum Topic

Dear,What is the implication if I tick or not tick the Caculate Multiple Critical Paths box in the Options, Calculation tab in MS Project 2007.I find that a lot of tasks become critical if I tick the box. Gary Lo

Jan 6, 2013

Creating the ultimate references.

Forum Topic

Greetings, We all know that when it comes to construction, it never ends of how many items of work it contains, how many construction methodologies it does have. A successful planner is a one who puts his schedule explaining the sequence of activitie...

Jan 7, 2013

Link Primavera & Crystal Report

Forum Topic

Hai All To  link Primavera SdK & Crystal Report  i did the below option 1.File -New - Report Expert -OK 2.Standand-Ok-Database-ODBC-Primavera P6 SDK-Admin-Admin (database Connected) 3.I want to create Tabular & Graphical Report for manpower histogram...

Jan 7, 2013

Excel-like features of Spider

Forum Topic

Vladimir, Rafael,In one of my questions about MSP, Vladimir answered, that it is very easy to implement Excel-like features in Spider.But so far I could not find how to do it.How would I achieve the following: say I have several Project-level paramet...

Jan 7, 2013

Expenses vs costs loading of programmes - Primavere P6 v.6.2

Forum Topic

Afternoon, More and more contractors programmes submitted are expenses loaded as opposed to costs loaded. Could someone give me a summary of pros and cons for doing so from both a contractor and an employer perspective? Thanks a lot.

Jan 7, 2013

Shop Fabrication

Forum Topic

Dear Planners...a simple question. A site established Piping Fab shop has to do 300,000 ID in 12 months with peak of 40,000 ID per month. What amount of piping mateterial (in Inch Dia) should be available in peak month:30% above target40% above targe...

Jan 8, 2013

Creating a new report with the wizard?

Forum Topic

 What i am needing to know how to do is create a report with the P6 report wizard that compares the early cost/early start versus late costs/Late finish directly from the P6 reports section. Can this be done? Im sorry, i am not the best person at exp...

Jan 8, 2013

Project Scheduling and Multiple Cash-Flows

Forum Topic

First of all,thank you Vladimir, Rafael for your help with my material ref-book problem, I managed to create ref-books and corporate ref-books for activities, material and resource assignments - very useful. Unfortunately today I got stuck on somethi...

Jan 8, 2013

Project task durations

Blog

 Probably the most common action undertaken by project planners everywhere is assigning a duration to a task; most of us do this almost automatically. Generally it is only when a dispute arises that the complex interaction of the factors discussed in...

Jan 9, 2013

MS Project Server - opinions?

Forum Topic

Hi there; my 1st ever post. I have a customer managing large project with multiple workstreams (or sub-projects) each with it's own manager. I'd normally recommend using Primavera P6 for this but the client wanted to use MS Project so that the manage...

Jan 9, 2013

Reasons to use multiple links between the tasks

Forum Topic

Dear all,possibility to use multiple links between the same 2 tasks is quoted as one of the Spider’s advantage. However the only application of this I could think of is to have SS and FF links from Activity 1 to Activity 2. In case Activity 2 is a ha...

Jan 28, 2013

Importing Into P6 V 8.2

Forum Topic

What type of files can you import into P6 V 8.2 eg. Microsoft Project etc? 

Jan 29, 2013

EXPERTS call. Baselines quibble.

Forum Topic

Hi thereThis is about baselines.If I don't assign any baseline and I use the current project as such, I have noticed that for the already finished and already started activities the program keeps the original baseline dates one day assigned to those....

Jan 29, 2013

Primavera Book

Forum Topic

Dear Planners,Can any one direct me to a good book with an example for Primavera enterprise?Regards,Moutaz

Jan 29, 2013

Export both Baseline+Current in one XER file?

Forum Topic

Dear All P6 Experts, I have my current schedule and I already assigned Basline to it. I try to export my current schedule as XER file and send it by e-mail but the person who import it to his computer he can't see my assigned baseline? Is there metho...

Jan 29, 2013