When exporting a report from Primavera P6 to an .xls file, any Budget values with a cost/unit of 1,000 or higher automatically shift to the wrong column (as shown in the attached screenshot).
Has anyone experienced this issue before, and could you please advise on how to fix it? Thank you very much for your assistance.