Thanks Jaco it worked. Regards from Munich Achim

Member for

21 years 2 months

Hi Achim



I WOuld Suggest you go to the Following Method.



1) Open a P3 Schedule (in Hours)

2) Create the 20 Systems as Activity

3) Calcultate the activity Durations



Example assume System has 80 loops and you said 40 loops a Day (Assume 8 working hours) This mean activty duration is 16 hrs



Do the system Inter Logic



Assign a Resource "Loops" BQ (Number of loops / Systems)



Press level (Assign the resource Loops) Make Normal & Max lvl 5 (40 loops /8 Hours)