Primavera Project Planner - P3 Member for 21 years Member for 21 years Submitted by Philip Jonker on Mon, 2005-06-20 15:54 Permalink RE: Resource leveling Hi achim, Forgotten me Member for 20 years 11 months Member for 20 years 11 months Submitted by Achim Kempf on Mon, 2005-06-20 11:32 Permalink RE: Resource leveling Thanks Jaco it worked. Regards from Munich Achim Member for 21 years 2 months Member for 21 years 2 months Submitted by Jaco Stadler on Mon, 2005-06-20 06:41 Permalink RE: Resource leveling Hi Achim I WOuld Suggest you go to the Following Method. 1) Open a P3 Schedule (in Hours) 2) Create the 20 Systems as Activity 3) Calcultate the activity Durations Example assume System has 80 loops and you said 40 loops a Day (Assume 8 working hours) This mean activty duration is 16 hrs Do the system Inter Logic Assign a Resource "Loops" BQ (Number of loops / Systems) Press level (Assign the resource Loops) Make Normal & Max lvl 5 (40 loops /8 Hours) Log in or register to post comments
Member for 21 years Member for 21 years Submitted by Philip Jonker on Mon, 2005-06-20 15:54 Permalink RE: Resource leveling Hi achim, Forgotten me
Member for 20 years 11 months Member for 20 years 11 months Submitted by Achim Kempf on Mon, 2005-06-20 11:32 Permalink RE: Resource leveling Thanks Jaco it worked. Regards from Munich Achim
Member for 21 years 2 months Member for 21 years 2 months Submitted by Jaco Stadler on Mon, 2005-06-20 06:41 Permalink RE: Resource leveling Hi Achim I WOuld Suggest you go to the Following Method. 1) Open a P3 Schedule (in Hours) 2) Create the 20 Systems as Activity 3) Calcultate the activity Durations Example assume System has 80 loops and you said 40 loops a Day (Assume 8 working hours) This mean activty duration is 16 hrs Do the system Inter Logic Assign a Resource "Loops" BQ (Number of loops / Systems) Press level (Assign the resource Loops) Make Normal & Max lvl 5 (40 loops /8 Hours)
Member for
21 yearsRE: Resource leveling
Hi achim,
Forgotten me
Member for
20 years 11 monthsRE: Resource leveling
Thanks Jaco it worked. Regards from Munich Achim
Member for
21 years 2 monthsRE: Resource leveling
Hi Achim
I WOuld Suggest you go to the Following Method.
1) Open a P3 Schedule (in Hours)
2) Create the 20 Systems as Activity
3) Calcultate the activity Durations
Example assume System has 80 loops and you said 40 loops a Day (Assume 8 working hours) This mean activty duration is 16 hrs
Do the system Inter Logic
Assign a Resource "Loops" BQ (Number of loops / Systems)
Press level (Assign the resource Loops) Make Normal & Max lvl 5 (40 loops /8 Hours)