Baseline from another File or Excel

Member for

18 years 7 months

Hi Alexandre,

 

Thank you for your response.

As I came to find out, there doesn't seem to be a way to do it the way I described.

My work around was to save the baseline in TILOS and progress the activities based on the other.

 

Cheers,

Member for

22 years 9 months

Hi Vasat,

I hoped that somebody had the solution, but I was wrong. I have found nowhere in Tilos the way to copy the schedule of one project to make it the baselin of another one, as it is possible in Primavera or Asta Powerproject

When you baseline a project, my experience is that you can only select activities in the current project.

Did you ask the question to Tilos people?

All the best,

Alexandre