Often neglegted to check is the Admin Preference -->Starting Day of Week settings where some planner use Monday if using 5 d/w calendar M-F but construction usually work 6 to 7d/w and use Saturday as First day of Week. This will affect the Planned % progress specially if the calendar is using 6d/w or 7d/w.
Another is the User Preference --> Time Distributed Data where P6 default for interval for time-distributed resource calculation is day. If using multiple calendar or mixed 24hr, 8hr, 12hr etc.. calendar, the accurate is set to hour instead of day.
Member for
16 years 3 monthsCheck the TIME settings also
Check the TIME settings also
Member for
9 years 8 monthsdennisinteresting. Resource
dennis
interesting.
Resource cost? dictionaries the same?
Member for
9 years 8 monthsdennisinteresting. Resource
dennis
interesting.
Resource cost? dictionaries the same?
Member for
2 years 9 monthsHi David, The P6 Fields
Hi David,
The P6 Fields affected in p6 for the Progress:
The Earned value settings have also been checked and they are the same:
"Budgeted Values with Current dates"
Regards
Dennis
Member for
2 years 9 monthsHi David, The P6 Fields
Hi David,
The P6 Fields affected in p6 for the Progress:
The Earned value settings have also been checked and they are the same:
"Budgeted Values with Current dates"
Regards
Dennis
Member for
2 years 9 monthsHi David, The P6 Fields
Hi David,
The P6 Fields affected in p6 for the Progress:
The Earned value settings have also been checked and they are the same:
"Budgeted Values with Current dates"
Regards
Dennis
Member for
19 yearsHi Dennis,Often neglegted to
Hi Dennis,
Often neglegted to check is the Admin Preference -->Starting Day of Week settings where some planner use Monday if using 5 d/w calendar M-F but construction usually work 6 to 7d/w and use Saturday as First day of Week. This will affect the Planned % progress specially if the calendar is using 6d/w or 7d/w.
Another is the User Preference --> Time Distributed Data where P6 default for interval for time-distributed resource calculation is day. If using multiple calendar or mixed 24hr, 8hr, 12hr etc.. calendar, the accurate is set to hour instead of day.
Member for
9 years 8 monthsWhat are the P6 field nnames
What are the P6 field nnames (e.g. Dutation % complete) that are affected?
And the Earned Value calculation settings for each gatabase under 'Admin Preferences'