Difference in Progress - Stand alone and Server

Member for

9 years 8 months

dennis

interesting.

 

Resource cost? dictionaries the same?

Member for

9 years 8 months

dennis

interesting.

 

Resource cost? dictionaries the same?

Member for

2 years 9 months

Hi David,

 

The P6 Fields affected in p6 for the Progress:

  • Schedule % Complete
  • Performance % Complete

The Earned value settings have also been checked and they are the same:

"Budgeted Values with Current dates"

 

Regards

Dennis

Member for

2 years 9 months

Hi David,

 

The P6 Fields affected in p6 for the Progress:

  • Schedule % Complete
  • Performance % Complete

The Earned value settings have also been checked and they are the same:

"Budgeted Values with Current dates"

 

Regards

Dennis

Member for

2 years 9 months

Hi David,

 

The P6 Fields affected in p6 for the Progress:

  • Schedule % Complete
  • Performance % Complete

The Earned value settings have also been checked and they are the same:

"Budgeted Values with Current dates"

 

Regards

Dennis

Member for

19 years

Hi Dennis,

Often neglegted to check is the Admin Preference -->Starting Day of Week settings where some planner use Monday if using 5 d/w calendar M-F but construction usually work 6 to 7d/w and use Saturday as First day of Week. This will affect the Planned % progress specially if the calendar is using 6d/w or 7d/w.

Another is the User Preference --> Time Distributed Data where P6 default for interval for time-distributed resource calculation is day. If using multiple calendar or mixed 24hr, 8hr, 12hr etc.. calendar, the accurate is set to hour instead of day.

Member for

9 years 8 months

What are the P6 field nnames (e.g. Dutation % complete) that are affected?

 

And the Earned Value calculation settings for each gatabase under 'Admin Preferences'