Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2022-07-13 16:08 Permalink because the schedule is based because the schedule is based on 8 hours per day based on the calendar excel does not consider TIMES it is just a day for day calculation P6 uses times in the background Member for 14 years 7 months Member for 14 years 7 months Submitted by jithin on Wed, 2022-07-13 15:16 Permalink Hi All, The default calendar Hi All, The default calendar for the Project was a 24 Hr calendar but when I changed that to 8 Hrs x 7 Days it started showing like the excel table. So why is it like that? Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2022-07-13 16:08 Permalink because the schedule is based because the schedule is based on 8 hours per day based on the calendar excel does not consider TIMES it is just a day for day calculation P6 uses times in the background
Member for 14 years 7 months Member for 14 years 7 months Submitted by jithin on Wed, 2022-07-13 15:16 Permalink Hi All, The default calendar Hi All, The default calendar for the Project was a 24 Hr calendar but when I changed that to 8 Hrs x 7 Days it started showing like the excel table. So why is it like that?
Member for
16 years 3 monthsbecause the schedule is based
because the schedule is based on 8 hours per day based on the calendar
excel does not consider TIMES it is just a day for day calculation
P6 uses times in the background
Member for
14 years 7 monthsHi All, The default calendar
Hi All,
The default calendar for the Project was a 24 Hr calendar but when I changed that to 8 Hrs x 7 Days it started showing like the excel table.
So why is it like that?