Doubt in Duration

Member for

16 years 3 months

because the schedule is based on 8 hours per day based on the calendar

excel does not consider TIMES it is just a day for day calculation

P6 uses times in the background

Member for

14 years 7 months

Hi All,

 

The default calendar for the Project was a 24 Hr calendar but when I changed that to 8 Hrs x 7 Days it started showing like the excel table.

 

So why is it like that?