Transfer Progress between 2 Programmes

Member for

16 years 3 months

open Rev 8 and make rev 7 a baseline

then select maintain baselines and select update

then from here you can choose what to update all activities or a filter or additional update options under Update options 

pick and choose what to update 

when you are done select Restore to put REV7 back into the selectable projects

Member for

22 years 9 months

Hello Mike,

I would rather export both schedules to Excel with all the necessary fields, make the adjustments there, then re-import the "new" schedule into P6

Alexandre

Member for

14 years 9 months

Hmnn... not that easy, because i have changed some duration and logic. 

I am wondering if its possible to open 2 programmes and use the global change to transfer the progress from 1 WBS to another 

 

Many thanks

Mike 

Member for

20 years 6 months

Don't you just make a copy of Rev 08 and then delete the new activities?